Application Support Case Studies

We present, anonymously, case studies of applications to electric utilities that we have handled on behalf of clients (industry, facility type, voltage class, and scope of the engagement). Our data center application cases number more than 200 (the total of preliminary studies, preliminary consultations, and formal applications), and we also handle extra-high-voltage projects (tens-of-MW class).

(01) — Case Index
8 CASES
Exterior of a corporate building in an urban area
Data CenterExtra-High / High Voltage

Data Center Developer: Preliminary Studies and Preliminary Consultations for Many Candidate Sites Applied for in One Batch

For many candidate sites spanning multiple utility areas, we prepared the application documents for supply-side preliminary studies and preliminary consultations and applied for them in one batch. A case in which we handled everything from responding to queries from the utilities and organizing the responses to organizing the inputs for deciding whether to continue or withdraw, and the move to the formal application.
Rooftop solar panel installation
Data CenterExtra-High Voltage

Renewable Energy and Battery Storage Developer: Supply-Side Preliminary Study for a Data Center Plan (Extra-High Voltage)

For a data center plan in the tens-of-MW class, supply-side preliminary studies were applied for with general transmission and distribution utilities in multiple areas. A case in which we handled preparation of the application forms and drawings and communication with the contact points.
Office building of a power generation business
Data CenterHigh Voltage

Real Estate Company: Supply-Side Preliminary Study for a High-Voltage Data Center Site

For the site of a small data center receiving power at high voltage, we handled everything from organizing the conditions to applying for the preliminary study. A case in which the document templates were standardized with a view to rolling out to multiple plots.
Solar and wind renewable energy facilities
Grid-Scale Battery StorageLow Voltage

Renewable Energy Developer: Grid Interconnection Applications for Low-Voltage Grid-Scale Battery Storage at Around 10 Sites

For low-voltage grid-scale battery storage, we prepared the documents for grid interconnection applications at around 10 sites. A case in which the information required for each site was managed in a single list and the applications were advanced one after another.
Solar power plant panels
Grid-Scale Battery StorageHigh / Low Voltage

Electrical Contractor: Connection Studies and Application Preparation for High-Voltage and Low-Voltage Grid-Scale Battery Storage

We handled the connection study applications for the high-voltage battery storage plants and application preparation for the low-voltage ones. A case in which we covered everything from proposing the equipment configuration to preparing the application documents and checking the content of the responses.
Solar panel installation and transmission and distribution infrastructure
Grid-Scale Battery StorageExtra-High Voltage

Battery Storage Developer: Connection Study for Extra-High-Voltage Grid-Scale Battery Storage (from Capacity Study and Single-Line Diagram)

A case in which, at the request of a company that owns the land, we handled everything from the capacity study and preparation of application documents such as the single-line diagram to the connection study application.
Exterior of a corporate building in an urban area
Co-located Battery StorageHigh Voltage

PPA and Battery Storage Operator: Connection Studies for Batteries Co-located with Commercial Facilities Applied for at Multiple Sites Simultaneously

For batteries co-located on customers' premises, high-voltage connection studies were applied for at multiple sites simultaneously. A case in which we handled everything from studying the equipment layout and sharing a progress management sheet to dealing with document replacements after the applications.
Rooftop solar panel installation
SolarHigh Voltage

EPC and Installation Contractor: Grid Interconnection Application for High-Voltage Self-Consumption Solar

For high-voltage self-consumption solar to be installed on the roof of a newly built building, we prepared and submitted the grid interconnection application documents. A case in which we dealt with corrections to the forms and the response was received about 1 week after submission.
(02) — Workflow & Automation

Workflow Systematization & Automation Support Cases

Solar power plant panels
Application Automation BPOSolar

Renewable Energy Producer A: Centralized Management of Grid Interconnection Application Progress

Turned application work that depended on individual staff into a system, building a structure that gives an at-a-glance view of progress across multiple projects. A case in which decision inputs from connection study through contract application are now managed at the same level of detail. Read Case Study
Solar and wind renewable energy facilities
Application Automation BPOGrid-Scale Battery Storage

Battery Developer B: Streamlining Document Preparation for Connection Studies

Enabled connection study applications for multiple sites to proceed in parallel by standardizing document preparation. A case in which differences in submission requirements were detected early, reducing documents sent back. Read Case Study
Solar panel installation and transmission and distribution infrastructure
DX / AI ConsultingSolar

O&M Provider C: Automating Daily Reports and Reporting Work with Generative AI

Supported everything from taking inventory of tasks to designing automation rules and embedding them in operations, reaching a state the client can sustain in-house. A case in which rework in daily monitoring and reporting was reduced. Read Case Study
Rooftop solar panel installation
Application Automation BPOSolar

Power Producer D: Standardizing Document Preparation for Connection Study Applications

Organized document preparation procedures that varied from project to project and standardized them into a form that can be handed over between staff. A case in which pre-submission review was moved earlier, limiting schedule delays. Read Case Study
Exterior of a corporate building in an urban area
Application Automation BPOGrid-Scale Battery Storage

Grid-Scale Battery Operator E: Visualizing Application Status Across Multiple Sites

Consolidated application progress, which differs by utility, into a single management sheet that can be shared internally. A case in which meeting preparation time was cut and decision-making accelerated. Read Case Study
Office building of a power generation business
DX / AI ConsultingSolar

Power Producer F: Automating the Preparation of Monthly Reports

Automated transcription and aggregation from inspection records so that staff can focus on verification. A case in which the end-of-month reporting crunch was leveled out, freeing up time for improvement activities. Read Case Study

Start by telling us how your work flows today.

It is fine even if your list of candidate sites and drawings are not yet complete. Please tell us the number of sites and the voltage class.
Contact Us