SERVICE — POWER PLANT

Grid Connection Applications
for Solar Power Plants

From low-voltage (under 50 kW) interconnection applications to preliminary consultations, connection studies and interconnection contract applications at high and extra-high voltage. We handle applications to the utility end to end: preparing the documents and attached drawings, submitting them, responding to inquiries and tracking progress. We cover all 10 general transmission and distribution utilities in Japan.

Published: October 7, 2026

(01) — Issue

What tends to go wrong
with solar applications.

01

Forms and practices differ
from utility to utility

Whether there is a web portal, the application form layout, the drawings required and the way inquiries are handled all differ by general transmission and distribution utility. For projects spanning several service areas, the same content has to be rebuilt in a different format each time.

02

Applications are sent back
for deficient documents

Omissions in single-line diagrams and layout drawings, and mismatches between the figures in the application and the drawings, are the main reasons applications are returned. Every return pushes the acceptance date back and affects the interconnection date.

03

Deadlines and sequencing
are left to one person

The application deadline after a connection study response, the sequencing with FIT/FIP business plan certification, and the deadline for land-use rights documents that became mandatory for high voltage and above from October 2026. The more sites there are, the more time deadline management alone consumes.

(02) — Scope

Procedures we handle

The flow differs by voltage class. We handle everything from low-voltage interconnection applications to connection studies and interconnection contract applications at high and extra-high voltage.

Procedure Low voltage High voltage Extra-high voltage
Low-voltage interconnection applicationLOW-VOLTAGE APPLICATION ✓ — —
Preliminary consultationPRELIMINARY CONSULTATION — ✓ ✓
Connection study applicationCONNECTION STUDY — ✓ ✓
Interconnection contract applicationINTERCONNECTION APPLICATION — ✓ ✓
Preparation of application documents and drawingsDOCUMENTS & DRAWINGS ✓ ✓ ✓
Inquiries, revisions and progress trackingFOLLOW-UP ✓ ✓ ✓

Facilities covered: solar power plants (low, high and extra-high voltage). Please also contact us about grid connection applications for other generation facilities such as wind, biomass and fuel cells. Area covered: all 10 general transmission and distribution utilities nationwide.
* Low voltage is outside the scope of connection studies and preliminary consultations, so the procedure starts with the interconnection application.
* Attached drawings are prepared for the application based on your design materials. Administrative procedures such as FIT/FIP business plan certification are handled together with our partner administrative scriveners (gyoseishoshi).

(03) — Process

How we work

01

Organize the project and sites

We confirm the voltage class, number of sites, planned interconnection date, FIT/FIP/non-FIT status and the design materials available, then set the approach in line with each utility's procedure.

02

Prepare and submit documents and drawings

We assemble the application documents and attached drawings in each utility's format and submit them. We fix the document template first so the same deficiency is not repeated across sites.

03

Handle inquiries and track progress

We respond to inquiries and returns from the utility and resubmit the corrected documents. We report the progress and deadlines for every site in a single list.

(04) — Rules 2026

Major rule changes affecting applications

The rules affecting solar power plant applications are being revised through 2026 and 2027. Application plans need to assume the following changes.

2026.10

Land-use rights documents become mandatory

For generation facilities at high voltage and above, interconnection contract applications accepted on or after October 1, 2026 must include documents proving land-use rights for the project site.

2026.11

Mid-period wheeling charge revision and new generator-side charge rates

A mid-period revision of wheeling charges takes effect on November 1, 2026, and the generator-side charge rates are also revised. Because this affects the economics of FIT/FIP plants, it should be checked alongside the interconnection schedule.

2027.04

JC-STAR ★1 becomes a grid connection requirement

For power conditioners and similar equipment in solar and battery systems, JC-STAR ★1 conformity becomes a grid connection requirement from April 2027 for high voltage and October 2027 for low voltage.

* Based on materials published as of October 2026. Rules and application forms are revised from time to time; please also check the latest materials from each general transmission and distribution utility and the relevant authorities when proceeding.

(05) — FAQ

Frequently asked questions

Q1

Can you handle applications for low-voltage (under 50 kW) solar plants?

Yes. Low-voltage solar plants follow the low-voltage interconnection application procedure defined by each general transmission and distribution utility. We prepare the application documents and attached drawings, submit them, respond to the utility's inquiries and track progress for each site.

Q2

Is a connection study application needed for low-voltage solar?

A connection study is a procedure for interconnection at high and extra-high voltage. Low voltage (under 50 kW) is outside the scope of connection studies and preliminary consultations, so the procedure starts with the interconnection application.

Q3

Can you also handle FIT/FIP business plan certification?

Business plan certification is an administrative procedure with the Ministry of Economy, Trade and Industry (Agency for Natural Resources and Energy), so we handle it together with our partner administrative scriveners. We manage the documents and deadlines together so it can proceed in parallel with the grid connection application to the utility.

Q4

Can we engage you for multiple sites at once?

Yes. We turn the differences between utilities' forms into document templates and report the progress of every site in a single list. The more sites a project has, the greater the reduction in rework.

Q5

Which areas do you cover?

We handle applications to all 10 general transmission and distribution utilities nationwide. Differences in each utility's web portal, forms and inquiry practices are built into our procedures and systems.

Q6

How much does it cost?

It depends on the voltage class, the number of sites and the scope of the engagement (document preparation only, or through submission and inquiry handling, for example), so we quote individually. Tell us the number of sites and the voltage class and we will give you an estimate.

Related services

For battery storage applications, see grid connection applications for low-voltage battery storage and grid-scale BESS (Japanese). For data center power supply applications, see Data Center Grid Connection Application Support.

Tell us the number of sites
and the voltage class.

Low-voltage solar applications, or how to approach connection studies at high and extra-high voltage. You are welcome to contact us while the project is still under review.

Contact Us