Power Checklist for Data Center Site Selection: What to Confirm About Power Supply Before Signing the Land Contract

For a data center site, confirm 4 points before signing the land contract: "the capacity that can be received," "the time until power is received," "the rough scale of the construction cost contribution," and "the deadlines and cancellation rules after the application." The process has two stages. First, screen the candidate sites using the maps published by the general transmission and distribution utilities; then check the remaining sites individually through a preliminary study or preliminary consultation. This article is for real estate companies, investors, and developers acquiring land for data centers, and sets out the items to confirm and their order on the basis of what we were able to confirm in materials published by TEPCO Power Grid and Kansai Transmission and Distribution.

This article is based on materials published as of November 17, 2026. Rules and application forms may be revised, so before proceeding, please also check the latest materials published by the relevant general transmission and distribution utility and other authorities.

Why Confirm Power Before the Land Contract?

The reason is that power conditions greatly affect the value of the land and, moreover, are hard to change once the land has been contracted. For a data center, neither the scale of the building nor the timing of operation can be decided until the capacity that can be received and the timing are settled. Even for land of the same area and the same price, the number of years until power is received and the amount of the contribution vary depending on whether the nearest substation has available capacity.

Extra-High-Voltage Supply Construction Can Take Years

TEPCO Power Grid publishes standard construction periods for extra-high-voltage (66 kV and above) supply construction (document dated May 2026). They are the period from application to energization and are indicative figures premised on a receiving voltage of 66 kV to 154 kV and 2 circuits.
Supply method Content of the work Standard construction period
Overhead transmission line New or rebuilt steel towers (fewer than 3 towers, route length of around 0.7 km) Around 42 months
Overhead transmission line Where a new substation or an additional transformer is involved Around 120 months
Underground transmission line New conduits and cables (around 3 km) Around 96 months
Underground transmission line Where a new substation or an additional transformer is involved Around 120 months
The document expressly states that these construction periods do not guarantee supply or the timing of implementation and do not take into account constraints such as land acquisition and permits and approvals. The 120 months is the standard construction period for construction of a new 154 kV substation and is stated to vary greatly with the voltage level and the number of transformers. Kansai Transmission and Distribution also states that the period for extra-high-voltage supply construction is discussed individually for each application and that a long period may be required.

Application Details Have Become Harder to Change After Applying

Since October 1, 2026, discipline on demand-side applications has been in effect under TEPCO Power Grid's Wheeling Service Provisions. If the application details change for the customer's own reasons before supply approval, that contract application is cancelled. It has become difficult to proceed by applying before the land is settled and changing the power receiving point or capacity afterward. Land and power need to be worked out in parallel.

Items That Can Be Confirmed from Published Information

What can be confirmed from published information is 3 points: whether there is available supply capacity around the candidate site, roughly what the indicative construction period is, and at what voltage power is likely to be received. All of these are indicative and are not a response for a specific site. Use them as material for a first screening.
Published material Publishing utility What can be confirmed
Welcome Zone Map TEPCO Power Grid For those seeking extra-high-voltage supply at 2,000 kW or more. Area, access, infrastructure, and construction period band (0 to 24 months, 25 to 48 months, 49 months or more, or not stated) for each industrial park. Maps of available supply capacity at 66 kV and 154 kV (as of December 2025)
Large-Scale Supply Potential Map TEPCO Power Grid Location and approximate construction period of substations with available capacity of 50 MW or more (154 kV and 66 kV) or 400 MW or more (275 kV). Dated October 30, 2026
Welcome Zone Map Kansai Transmission and Distribution For those seeking high-voltage or extra-high-voltage supply. Search by area and access conditions for areas that can be supplied relatively quickly and at low cost
Supply Availability Area Map Kansai Transmission and Distribution Covers a standard voltage of 70 kV and contracted power of 10,000 kW or more. Available supply capacity and construction period for the area around each substation, and indicative suppliable capacity, construction period, and construction contribution by location. As of September 2026

TEPCO Power Grid's Published Maps

TEPCO Power Grid's Welcome Zone Map is a page on which industrial parks can be searched by incentive schemes, area, access, land price, infrastructure, and construction period. Available supply capacity is shown separately for 66 kV and 154 kV, in graduated display and heat map display (information as of December 2025). The company notes that available supply capacity varies with grid conditions and new supply, and that the supply voltage may be 66 kV or 154 kV depending on the contracted power and the supply point. For those seeking 50,000 kW or more, the Large-Scale Supply Potential Map is indicated. For substations with large available capacity, it shows an approximate construction period of around 5 years within a radius of about 1.5 km of the substation and around 10 years within a radius of about 6 km (in the case of 154 kV and 66 kV). This construction period too is an indicative figure by distance, premised on the stage at which the location and specifications of the receiving equipment have been decided, and constraints such as roads, rivers, underground utilities, and land acquisition are not taken into account.

Kansai Transmission and Distribution's Published Maps

Kansai Transmission and Distribution's Supply Availability Area Map consists of wide-area versions for large-scale supply (around 100 to 300 MW) and small-to-medium-scale supply (around 10 to 50 MW), a detailed version showing areas with available capacity of 10 MW or more and a construction period of around 3 to 5 years, and other maps. The detailed version distinguishes available capacity by color: 10 to under 30 MW is green, 30 to under 50 MW is orange, and 50 MW or more is red. The construction period referred to in this map is the period from payment of the construction cost contribution, after receipt of the wheeling supply and basic contract application form, to the start of transmission. Note that the definition differs from TEPCO Power Grid's standard construction period (from application to energization). The company states that the construction period and available capacity are a guide and may change in the detailed study at the time of application. Supply may be possible even in unpublished areas, in which case an application for a preliminary study is required. The differences between each company's maps are summarized in our guide to the Welcome Zone Maps by general transmission and distribution utility.

Confirm the Voltage Class in the Provisions and Each Company's Guidance

The voltage at which power is received is determined in accordance with the general transmission and distribution utility's Wheeling Service Provisions. TEPCO Power Grid presents 2,000 kW or more as the scope of extra-high-voltage supply. Kansai Transmission and Distribution's Supply Availability Area Map covers a standard voltage of 70 kV and contracted power of 10,000 kW or more. Which voltage class the assumed contracted power falls into also bears on the scale of the building and receiving equipment and on the calculation of the contribution. For the approach to the classes, see Data Center Receiving Capacity and Extra-High-Voltage Supply (Japanese).

Items to Confirm Through a Preliminary Study

What a preliminary study can confirm is whether facility work is required to supply the site and, if so, the type of work. If you also want to know the construction period and an estimate of the contribution, a more in-depth study or consultation is needed. How much you can find out differs by utility and by the stage of the procedure.

Kansai Transmission and Distribution

Kansai Transmission and Distribution's supply-side preliminary connection study covers high voltage and above. Parties other than retail electricity suppliers can also apply. Fill in the prescribed Excel form and send it by email with the drawings needed for the study. The response is given within 2 weeks of acceptance of the application as a rule and indicates whether construction is required and, if so, the type of work (access facility work, electricity meter work, or communication facility work). If you want to know more, you can also receive a detailed study by requesting it on the preliminary study application form. The response takes around 3 months from the application and indicates an outline of the work, the required construction period, an estimate of the construction cost contribution, the conditions of supply, and so on. The company states that the response to the detailed study reflects the position at the time of the response and does not guarantee future available supply capacity. It is guaranteed at the point of supply approval, following the supply study after the contract application. Note that applying for a preliminary study is not mandatory.

TEPCO Power Grid

TEPCO Power Grid places the preliminary consultation at the start of the procedure for new high-voltage and extra-high-voltage installations and recommends it. It is requested through the web reception when you wish to discuss matters such as the service entrance location and the desired supply start date. The customer and the licensed electrical contractor can also consult at this stage. The preliminary study that follows is a procedure used when you wish to confirm whether construction is required and the type of construction before the contract. The company directs applicants to confirm the construction period for a specific supply point through the preliminary consultation. In the preliminary studies we have handled, even sites that appeared to have available capacity on the published maps sometimes receive a response that reinforcement work is required. This is because available supply capacity varies with grid conditions and new supply. The detailed flow of the procedure is summarized in our guide to the supply-side preliminary connection study.

Risks Relating to the Contribution and Deadlines

There are 2 risks to grasp before the land contract: the construction cost contribution turning out larger than assumed, and the application being cancelled because a deadline after the application could not be met. Both bear directly on the conditions for the land and on the funding plan.

Getting a Sense of the Scale of the Construction Cost Contribution

TEPCO Power Grid publishes a simulation of the construction cost contribution for those seeking a 66 kV main line and standby line contract. Entering the route length of the work (m) and the newly added contracted power (kW) gives the approximate amount for an overhead line and for an underground line respectively. The assumptions shown on the page are as follows.
  • The unit construction cost is JPY 198.0/(100 m·kW) for overhead lines and JPY 594.0/(100 m·kW) for underground lines (including an amount equivalent to consumption tax, etc.)
  • For the main line, the amount borne by the company (JPY 5,500/kW × newly added contracted power) is deducted from the construction cost. If the result of the calculation is negative, the amount is JPY 0
  • For the standby line, where it is installed on the same supporting structures at the same time, 20% of unit construction cost × route length × contracted power
In the calculation examples on the page, the approximate amount is JPY 34,936,000 for a 66 kV overhead line with contracted power of 20,000 kW and a straight-line route length of 3,000 m (50 m on the premises), and JPY 39,688,000 for a 66 kV underground line with contracted power of 20,000 kW and a shortest distance along roads of 1,000 m (50 m on the premises). Because the unit cost for underground lines is 3 times that for overhead lines, the amount becomes large even over a short distance. These amounts are reference values. The actual distance and contribution are decided at the stage when a proposed supply route is presented through consultation with the company. In addition, the simulation is premised on 66 kV, and a separate preliminary consultation is stated to be required for 154 kV and 275 kV. Kansai Transmission and Distribution shows indicative construction contributions by location in the "Contribution and Construction Period Quick-Reference Map" of its Supply Availability Area Map.

The Discipline Effective October 1, 2026

TEPCO Power Grid applied for approval of changes to its Wheeling Service Provisions on June 24, 2026 and received approval on July 22. The effective date is October 1, 2026. For demand-side grid connection, the following 2 points are what we were able to confirm in the company's published materials.
  • Where a change to the application details arises for the customer's own reasons before supply approval (formation of the contract), that contract application is cancelled
  • The deadline from supply approval to payment of the construction cost contribution is set at within 3 months, and if it is exceeded, that contract application is cancelled
The background is "speculative capacity reservation" of grid capacity. The materials of the Agency for Natural Resources and Energy's Next-Generation Power Grid Working Group (April 16, 2026) set out that if a state in which only part of the grid capacity that has been secured is used continues, it leads to unnecessary facility build-out and longer periods until grid connection. The materials also present a proposal to allow minor changes that do not affect the supply measures work or the result of the technical study. Care is needed regarding land-use rights. In the company's published materials, the requirement to submit documents evidencing land-use rights for the project site (within 2 months of interconnection approval) is part of the discipline on the generation side (non-FIT, non-FIP generation). For demand-side applications, we did not find the same document submission requirement within the materials we checked this time. However, a change in the power receiving point constitutes a change to the application details. Applying without a clear prospect of securing the land means carrying the risk of cancellation. For details, see Data Center Supply Start Dates and Application Cancellation Rules. For the status of implementation in other areas, please check each company's provisions and guidance.

Power Checklist for Data Center Sites

We have compiled the items to confirm before the land contract into 12 items. The "Basis" column distinguishes items based on published materials or the provisions from items that are not prescribed by the rules but that should be confirmed in practice.
Item to confirm How to confirm When to confirm Basis
1. Assumed contracted power and voltage class Business plan, Wheeling Service Provisions, each company's guidance Before starting to look for candidate sites Provisions and each company's published materials
2. Position on the published maps Welcome Zone Map, Supply Availability Area Map, Large-Scale Supply Potential Map When candidate sites are identified Each company's published materials
3. Distance to the nearest substation and transmission line Published maps, on-site check When candidate sites are identified The construction periods and contributions in published materials are premised on distance
4. Indicative construction period Published maps, document on standard construction periods First screening Each company's published materials (indicative, not a guarantee)
5. Desired timing of power receiving Cross-checking the business plan against the indicative construction period First screening Practical point to confirm
6. Receiving method (1 circuit or 2 circuits, main line and standby line) Business plan, preliminary consultation Before the preliminary study The construction periods and contributions in published materials are premised on 2 circuits
7. Rough scale of the construction cost contribution Simulation, Contribution and Construction Period Quick-Reference Map First screening to preliminary study Each company's published materials (reference values)
8. Application for a preliminary study or preliminary consultation Each company's prescribed forms, web reception When candidate sites have been narrowed down Each company's guidance (not mandatory at Kansai Transmission and Distribution)
9. Whether construction is required and its type Response to the preliminary study Before the land contract Each company's guidance
10. Status of rights to the land and contract terms Registry, discussions with the seller and landowners When negotiating the land contract Practical point to confirm (a change to the application details is subject to cancellation)
11. Funding plan that meets the payment deadline for the contribution Internal approval procedures, fundraising schedule Before the contract application TEPCO Power Grid's provisions (within 3 months of supply approval)
12. Phased expansion plan, emergency generation equipment, and status of consideration of the retail electricity supplier Business plan, facility design, discussions with retail electricity suppliers Before the contract application Practical point to confirm

How to Use the Checklist

Items 1 to 7 can be advanced with published information and internal plans alone, except where the preliminary consultation is used for item 6, and no application is needed. Items 8 to 9 require an application to the general transmission and distribution utility, and the response takes a number of days. Items 10 to 12 concern the terms of the land contract and of the contract application. A supplementary note on the retail electricity supplier in item 12. In TEPCO Power Grid's procedures, the wheeling supply application is made mainly by the retail electricity supplier. Kansai Transmission and Distribution also advises applying through the retail electricity supplier on a schedule with time to spare. TEPCO Power Grid's preliminary consultation can be requested by the customer or a licensed electrical contractor, and its preliminary study is applied for by a retail electricity supplier or similar party. Kansai Transmission and Distribution's preliminary study can also be applied for by parties other than retail electricity suppliers. The contract application is made mainly through a retail electricity supplier. Starting to consider this early makes the timing of the application less likely to slip.

How to Proceed When Comparing Multiple Candidate Sites

Compare multiple candidate sites by lining up the same items in the same order. The order is to look broadly with the published maps and then deeply with the preliminary study. Proceeding in the following 4 steps reduces rework.
  1. Align the conditions. Decide the assumed contracted power, the desired timing of power receiving, and the receiving method first. If the conditions differ from one candidate site to another, they cannot be compared.
  2. Make a list using the published maps. For each candidate site, tabulate the available supply capacity on the map, the indicative construction period, and the distance to the nearest substation. Also record the as-of date of the map (the year and month of the information).
  3. Narrow down to a few sites and check them individually. For candidate sites that fit the business plan, apply for a preliminary study or preliminary consultation. Add the content of the response and the response date to the table.
  4. Reflect the response in the terms of the land contract. Starting with the candidate sites for which there is a clear prospect of receiving power, work out the terms of the purchase or lease.
When comparing across areas, pay attention to the definitions of terms. For example, as to the construction period, TEPCO Power Grid's standard construction period is the period from application to energization, whereas Kansai Transmission and Distribution's Supply Availability Area Map uses the period, after receipt of the application form, from payment of the construction cost contribution to the start of transmission. Lining up the figures alone can lead to a wrong decision. We assist with everything from organizing the published information for each candidate site to preparing the application documents for the preliminary study and interpreting the response. Fees are quoted individually according to the number of sites, the voltage class, and the scope of work. For details, see Data Center Grid Connection Application Support. The differences from site selection for battery storage plants are explained in Site Selection for Battery Storage Plants and Grid-Side Constraints (Japanese).

Frequently Asked Questions About Confirming Power for Data Center Sites

How long does it take to confirm power?

The first screening with the published maps can be done the same day once the location of the candidate site is known. Confirmation for a specific site takes time. At Kansai Transmission and Distribution, the response to the supply-side preliminary connection study is stated to be given within 2 weeks of acceptance of the application as a rule, and the detailed study to take around 3 months from the application. For the periods in other areas, please check each company's guidance. Land negotiations are easier to advance if the schedule is set to include this period of waiting for the response.

Is it too late to apply for power after contracting the land?

It cannot be said categorically to be too late, but the risk becomes greater. Extra-high-voltage supply construction can take years, and even if it turns out that the timing or capacity at which power can be received does not fit the business plan, land that has already been contracted cannot easily be given up. The published maps can be checked even before the land is contracted. TEPCO Power Grid's preliminary consultation can be requested by the customer, and Kansai Transmission and Distribution's preliminary study can also be applied for by parties other than retail electricity suppliers. We recommend the order of first confirming the outlook for power and then reflecting it in the terms of the purchase contract or lease contract.

How should we proceed if we have many candidate sites?

A realistic approach is to narrow down using the published maps before applying, rather than applying for a preliminary study for every candidate site. First, list the available capacity and indicative construction period using each company's Welcome Zone Map or Supply Availability Area Map. Next, narrow down to a few candidate sites that fit the capacity and timing of the business plan, and check those sites individually through a preliminary study or preliminary consultation. Kansai Transmission and Distribution asks applicants to refrain from applications that are not backed by an actual business.

Can land considered for a battery storage plant be used as a data center site?

Not necessarily as it is. In our practical understanding, a study for a battery storage plant includes generation-side (reverse power flow) available capacity, whereas a data center is assessed on demand-side available supply capacity. TEPCO Power Grid also separates the map for customers from the Available Capacity Map for generators and states that available capacity on the generation side differs from available capacity for supply. The response for a battery storage plant cannot be reused, and a preliminary study needs to be carried out afresh as a demand-side facility.

Related Articles and Services

References (Primary Sources)

* The content of this article is current as of its publication date. Later changes to rules or their operation may not be reflected, so please check the official announcements of each organization for the latest information. If you need your project checked against the latest rules, please feel free to contact us.

Reviewed by
General Manager, Energy Solutions Division, Grid Work Inc.

A licensed electrical engineer with more than ten years at a Japanese electric utility, working on substation design, construction and management. Draws on hands-on experience from the grid-operator side to support grid connection applications for power plants and grid-scale batteries, and to prepare application documents that avoid rejections.

How does this apply to your project?

Grid connection procedures differ by utility area and facility conditions. Questions at the “what would this mean for our case?” stage are welcome. Our team knows the utility-side process.