Column

What Is the Supply-Side Preliminary Connection Study? How to Apply for a Data Center Preliminary Study, Response Periods, and Submitting Multiple Candidate Sites Together

The supply-side preliminary connection study (supply-side preliminary study) is an optional procedure in which, before a demand facility such as a data center receives a supply of electricity, the general transmission and distribution utility is asked to confirm whether construction work is required for the supply and what type of work it would be. Kansai Transmission and Distribution (for the response to the detailed study) and Kyushu Electric Power Transmission and Distribution expressly state that the response does not guarantee available supply capacity. It is a separate procedure from the "connection study" for generation equipment, with a different place to apply and different forms. This article is for developers with multiple candidate sites for data centers and summarizes what we were able to confirm in materials published by the Organization for Cross-regional Coordination of Transmission Operators (OCCTO) and 5 general transmission and distribution utilities.

This article is based on materials published as of November 17, 2026. Rules and application forms may be revised, so before proceeding, please also check the latest materials published by the relevant general transmission and distribution utility and other authorities.

What Is the Supply-Side Preliminary Connection Study?

The supply-side preliminary connection study is a procedure in which, ahead of the wheeling supply contract (the formal application for power supply), the general transmission and distribution utility is asked to study whether construction work is required to supply the demand site and, if so, what type of work. Applying is optional. The utilities' explanations are largely the same. Kansai Transmission and Distribution describes it as a procedure that studies whether facility work is required to provide wheeling supply and, if work is required, the type of work (access facility work, electricity meter work, or communication facility work), and expressly states that "the supply-side preliminary connection study application is not mandatory." Chubu Electric Power Grid likewise states that, on request, it studies whether work on the facilities for the demand site is required and the kind of work. The name differs slightly from company to company. Kansai Transmission and Distribution, Chubu Electric Power Grid, and Kyushu Electric Power Transmission and Distribution call it the "supply-side preliminary connection study," while TEPCO Power Grid and Tohoku Electric Power Network call it the "preliminary study." Council materials of the Agency for Natural Resources and Energy also place a "preliminary study (optional)" at the stage before the contract application. The shortened name "supply-side preliminary study" is also used in practice, but it refers to the same thing.

How It Differs from the Generation-Side Connection Study

Those with experience developing battery storage plants or solar need to take care, as it is easily confused with the generation-side "connection study." According to OCCTO's "Flow of Grid Access for Generation Equipment, etc." (June 2026), the generation-side connection study is a mandatory procedure carried out before the contract application, and payment of a study fee is required. According to each company's published materials, the supply-side preliminary study is optional, and some companies set the response period at within 2 weeks as a rule.
Item Supply-side preliminary connection study (demand side) Connection study (generation side)
Subject Supply to demand facilities (data centers, factories, etc.) Grid interconnection of generation equipment, etc. (including batteries)
Position Optional. Those who wish to do so apply ahead of the contract application Mandatory. The applicant proceeds to the contract application on the basis of the response
Study fee Tohoku Electric Power Network (extra-high voltage) states that it does not collect one, and Kyushu Electric Power Transmission and Distribution states that none is required. For other companies, please confirm with each utility Payment is required for each study at each power receiving point (1 point, 1 study)
Period until the response Within 2 weeks as a rule at Kansai, Kyushu, and Tohoku (extra-high voltage) Within 3 months of the acceptance date as a rule (within 2 months as a rule in some cases)
Main content of the response Whether construction is required and, if so, the type of work Whether interconnection is possible, an outline of the work, the estimated construction cost, the estimated construction cost contribution, the required construction period, and so on
Forms Supply-side preliminary connection study application form, preliminary study response form Generation-side forms such as the connection study application form
Note that for grid-scale battery storage, it is a requirement that the contract applications on both the generation side and the demand side be accepted at the same time. If you are considering only the power supply for a data center, it is enough to look at the demand-side procedures alone. The overall flow of the power supply application is set out in The Data Center Grid Connection (Power Supply) Application Flow.

Who Applies, and on Which Form?

The application is made to the general transmission and distribution utility (or distribution utility) whose supply area includes the candidate site. As for forms, OCCTO publishes common forms, and each utility provides its own forms or application system (Tohoku Electric Power Network provides that its application form and forms follow those of OCCTO). OCCTO's list of forms includes the following 4 under the category "Grid access for demand facilities (supply side), etc." The heading of the category reads "handled by the general transmission and distribution utility or distribution utility to which the facility connects."
Form name When it is used
Supply-side preliminary connection study application form When applying for a preliminary study
Preliminary study response form When the general transmission and distribution utility responds with the result of the preliminary study
Wheeling supply and basic contract application form When applying for a wheeling supply contract (the formal application)
Demand facility contract application response form When responding to a contract application

Can the Customer Itself Apply?

The scope of who may apply is described differently in each area. Kansai Transmission and Distribution and Kyushu Electric Power Transmission and Distribution state that customers other than retail electricity suppliers can also apply. Tohoku Electric Power Network's Grid Access Study Standards (Extra-High Voltage) define the study as one carried out at the request of a party seeking demand-side grid interconnection or of the customer. TEPCO Power Grid, in its guidance on procedures for new high-voltage and extra-high-voltage installations, gives the applicant for the preliminary study as "retail electricity suppliers and similar parties." As an entry point for cases where the customer, a licensed electrical contractor, or similar party wishes to discuss the service entrance location and the desired supply start date, there is a separate web reception for the "preliminary consultation." When you are in the early stage of development and the retail electricity supplier has not been decided, confirming in advance which entry point to use avoids redoing work.

Application Methods and Response Periods by Area

The 3 companies for which we were able to confirm a response period of within 2 weeks as a rule in the published materials are Kansai Transmission and Distribution, Kyushu Electric Power Transmission and Distribution, and Tohoku Electric Power Network (extra-high voltage). The application method differs from company to company: email, a dedicated system, or a web form.
Area Application method Response period Points to note that we were able to confirm
TEPCO Power Grid For the preliminary study, fill in the prescribed form and send it as an attachment to the email address for high-voltage applications (the applicant is "retail electricity suppliers and similar parties"). The preliminary consultation is requested through the web reception service The response period for the preliminary study is not stated on the guidance page we checked. For the preliminary consultation, the aim is to make contact within 5 business days from the day after the registration completion email The preliminary study is a recommended procedure before the contract application. For extra-high voltage (66 kV and above), the guidance is to request a preliminary consultation if you want to know the construction period for a specific point
Kansai Transmission and Distribution Fill in the "Supply-side preliminary connection study application [common to extra-high voltage and high voltage]" (Excel) and send it with drawings to the dedicated application email address Within 2 weeks of receiving the application as a rule. The detailed study takes around 3 months Parties other than retail electricity suppliers can also apply. Drawings include a vicinity map of the service entrance and a plan view. Because the separate document "How to apply" also contains the wording "within 3 months," confirm at the time of application
Chubu Electric Power Grid Apply through the dedicated "supply-side preliminary connection study application system." If it cannot be used, submit the application form to the Network Service Center A response is given promptly once the study is complete. For details, the guidance is to check in the application system Calculate an indicative appropriate capacity for power-factor correction capacitors with the appropriate SC capacity study tool and submit it together with the application
Tohoku Electric Power Network (extra-high voltage) Apply to the contact point (Network Service Department). The forms follow those of OCCTO Within 2 weeks of acceptance as a rule No study fee is collected. The acceptance date is the day on which application documents free of deficiencies are received. A letter of consent from the customer to the disclosure of information to the applicant (on the prescribed form) is submitted together with the application
Kyushu Electric Power Transmission and Distribution Fill in the "supply-side preliminary connection study application form" and email it to the Wheeling Contract Group of the Network Service Center. For a new installation, also submit a map of the surrounding area or similar document that identifies the demand site 2 weeks from acceptance for whether construction is required and the content of the work. For the detailed study, an indicative period is given separately Parties other than retail electricity suppliers can also apply. No study fee is required. If 1 applicant submits a large number of applications, the number may be adjusted
Hokkaido, Hokuriku, Chugoku, Shikoku, and Okinawa We have not been able to check the original sources for this article. Please check each company's guidance
At TEPCO Power Grid, note that the "preliminary study" and the "preliminary consultation" stand side by side as separate entry points. The company's "Overview of applications for high-voltage demand-side customers" (September 2026) asks applicants to carry out a preliminary consultation and preliminary study when applying, because the construction period required differs depending on the content of the work and the supply location. Its document on standard construction periods for extra-high voltage also directs those who want to know the construction period for a specific supply point to request a preliminary consultation. Chubu Electric Power Grid also has a power receiving guidebook for extra-high-voltage customers. It sets out a flow in which the customer notifies the contact point when a plan emerges and a preliminary study of supply measures is carried out ahead of the application, and it states that the result of the preliminary study may change at the time of the formal application. The guidebook states that the response with the supply study result (whether interconnection is possible, the supply voltage, an outline of the work, the construction cost contribution, the construction period, and so on) normally takes 30 business days or more. For the differences in contact points between areas, see also Grid Interconnection Application Contact Points and Differences Among the 10 General Transmission and Distribution Utilities (Japanese).

Submitting Multiple Candidate Sites Together in Practice

When there are multiple candidate sites, the basic approach is to assemble the materials as 1 application per site and track all the sites in 1 management sheet. What matters is not so much submitting them together as aligning the assumptions so that the responses can be compared. There is a point to note regarding the number of applications. Kyushu Electric Power Transmission and Distribution states that where 1 applicant submits a large number of applications, it may adjust the number from the standpoint of fairness. Please confirm with each general transmission and distribution utility before applying how the number of applications is handled at other companies. Rather than submitting a large number without narrowing down the candidate sites, screening them first with public information such as the Welcome Zone Map moves things along faster in the end. For large-scale demand such as data centers (tens to hundreds of MW), Kansai Transmission and Distribution publishes the "Supply Availability Area Map," which lets you check the approximate construction period and the approximate construction cost contribution based on past studies. TEPCO Power Grid also publishes a Welcome Zone Map for those seeking extra-high-voltage supply at 2,000 kW or more.

Items to Organize for Each Site

We recommend listing the following items for each site before applying. These are not the entry fields of the forms themselves, but a way of organizing information for internal comparison and progress management.
Category Items to organize
Site information Name of the candidate site, location (lot number), the general transmission and distribution utility for the supply area, and the status of securing the land
Power receiving conditions Assumed receiving capacity (contracted power), desired receiving voltage, desired timing of the start of supply, and, if capacity is to be increased in stages, the capacity and timing of each stage
Attachments Whether a vicinity map of the service entrance, plan view, single-line diagram, and map of the surrounding area exist, and their versions
Application status Application date, acceptance date, expected response date, response date, contact point in charge, and history of inquiries
Content of the response Whether construction is required, the type of work, whether there is a detailed study, the approximate construction period, the estimated construction cost contribution, and any conditions attached

How to State Receiving Capacity and Desired Timing

If receiving capacity is stated on different assumptions for each site, the responses cannot be compared. Separate the capacity ultimately required from the capacity required at initial operation, and apply the same approach to all sites. In TEPCO Power Grid's preliminary consultation, the guidance is to enter the maximum capacity anticipated as the capacity applied for. For the desired timing, state a date worked back from the schedule for completion of the building and delivery of equipment. Stating an early date with no basis does not bring the response forward and becomes a cause of changes later. Chubu Electric Power Grid's power receiving guidebook asks customers to notify it again if plans such as the contracted power or the desired power receiving date change. The approach to capacity and voltage class is explained in Data Center Receiving Capacity and Extra-High-Voltage Supply (Japanese).

Key Points for Progress Management

The starting point of the response period is the "acceptance date." Tohoku Electric Power Network defines the acceptance date as the day on which application documents free of deficiencies are received. Kansai Transmission and Distribution's "How to apply" lists the application form (Excel) and the drawings needed for the study as the materials required for acceptance. If drawings are missing or entries are omitted, the starting point is pushed back by that much. Where sites span multiple areas, the entry points differ (email, a dedicated system, or a web form), so recording the date of sending and the date on which acceptance was confirmed separately keeps you from misjudging the expected response date. Materials from Kansai Transmission and Distribution (detailed study), Chubu Electric Power Grid, and Tohoku Electric Power Network set out a practice of notifying the applicant of the reason, the progress, and the outlook when a response is expected to exceed the deadline. In the preliminary studies we have handled, acceptance sometimes takes time because of replacement of drawings or additional inquiries. We take on this kind of document organization and dealing with contact points through our Data Center Grid Connection Application Support.

What the Response Tells You and What It Does Not

What the response to a preliminary study tells you is whether construction is required for the supply and, if so, the type of work. Whether it also tells you the construction period and the amount of the construction cost contribution depends on the company and the depth of the study. It is not a promise of supply.
Category Content
What the preliminary study tells you Whether construction required for the supply is needed, and its type: access facilities (access transmission line), electricity meters, communication facilities, and so on
What a detailed study or similar tells you In Kansai Transmission and Distribution's detailed study: an outline of the work, the required construction period, an estimate of the construction cost contribution, the conditions of supply, and so on. At Kyushu Electric Power Transmission and Distribution as well, a more detailed study can be requested if desired
What it does not tell you or promise Securing of future available supply capacity, a guaranteed supply start date, or a final amount for the construction cost contribution
Kansai Transmission and Distribution states that the response to the detailed study reflects the position at the time of the response and does not guarantee future available supply capacity. It is guaranteed at the point when, after the contract application, the supply study is carried out and supply approval is received. It also expressly states that the result of the response may change. Kyushu Electric Power Transmission and Distribution likewise states that the response to the preliminary study does not guarantee available supply capacity. The same caution applies to the construction period. TEPCO Power Grid's document on standard construction periods for extra-high voltage (66 kV and above) states that, after the response to the preliminary consultation, a detailed study is carried out at the time of the supply application, and that depending on its result the outcome may differ greatly from the response given at the preliminary consultation. The construction periods shown in that document are approximations that assume an application made with the location and specifications of the receiving equipment finalized, and they do not guarantee supply within the period. When you receive the response, do not decide on the basis of the binary "no construction required" or "construction required" alone; check which type of work was found to be required and what capacity and timing the study assumed. How to read the response and the next decisions are also covered in How to Proceed After Receiving the Preliminary Study Response.

Moving from the Preliminary Study to the Formal Application (Wheeling Supply Application)

Receiving the response to a preliminary study does not move the procedure forward automatically. To receive supply, you need to make a separate contract application for wheeling supply and obtain supply approval following the general transmission and distribution utility's supply study. Kansai Transmission and Distribution states that where a contract application is made following the result of a preliminary study, it begins the wheeling supply study after acceptance of the contract application is complete. Because an application cannot be accepted if there are deficiencies in its content, and the desired transmission date may then not be met, it asks applicants to apply through the retail electricity supplier with time to spare. TEPCO Power Grid's overview of applications for high-voltage demand-side customers (September 2026) is a document covering high voltage, and the "supply preliminary study response form" is included in its list of documents to be submitted with the application, marked with a "△". Because the treatment at extra-high voltage cannot be confirmed from that document, keep the preliminary study response form and confirm at the time of the formal application whether it needs to be submitted.

The Discipline Required at the Formal Application Stage

For formal applications for large-scale demand, ensuring discipline has been discussed at a council of the Agency for Natural Resources and Energy. The document dated April 16, 2026, "Ensuring discipline for localized large-scale demand," identifies the issue that when a customer applies without having a clear outlook on matters such as the power receiving point, the general transmission and distribution utility cannot begin its technical study and consultations stall. As proposed responses, the document as of April 16, 2026 lists encouraging contract applications to be made once supply conditions such as the power receiving point are in place, cancelling the contract application where there are deficiencies or changes attributable to the customer, and allowing minor changes that do not affect matters such as the result of the technical study. It also presents a proposal on the treatment of grid capacity where the supply start date is postponed. Subsequently, TEPCO Power Grid applied for approval of changes to its Wheeling Service Provisions on June 24, 2026 and received approval on July 22. Since October 1, 2026, it has implemented the treatment of cancelling the contract application where the application details change for the customer's own reasons before supply approval. Please confirm the timing of implementation in other areas and the details of the requirements in our article Data Center Supply Start Dates and Application Cancellation Rules and in the latest provisions and guidance of each general transmission and distribution utility. In light of this discussion, it is practical to treat the preliminary study stage as a preparation period for settling the sites and conditions to be put forward in the formal application. The sequence is to compare candidate sites through preliminary studies and take forward to the formal application only those sites for which the power receiving point, capacity, and desired timing have been settled.

Frequently Asked Questions About the Supply-Side Preliminary Connection Study

Is there a fee for the supply-side preliminary connection study?

Tohoku Electric Power Network's Grid Access Study Standards (Extra-High Voltage) provide that no study fee is collected for the preliminary study. Kyushu Electric Power Transmission and Distribution's guidance also states that no study fee is required. For the treatment at other companies, please confirm with each general transmission and distribution utility before applying. Note that the generation-side connection study is a procedure for which payment of a study fee is required, and it is treated differently from the supply-side preliminary study.

If we receive a response to the preliminary study, is the capacity reserved?

No. Kyushu Electric Power Transmission and Distribution states that the response to the preliminary study does not guarantee available supply capacity. Kansai Transmission and Distribution also states that the response to the detailed study reflects the position at the time of the response and does not guarantee future available supply capacity, and that it is guaranteed by supply approval following the supply study after the contract application. If the surrounding circumstances change after the response, the result may change.

Can the customer itself apply even if the retail electricity supplier has not been decided?

Kansai Transmission and Distribution and Kyushu Electric Power Transmission and Distribution state that customers other than retail electricity suppliers can also apply. TEPCO Power Grid gives the applicant for the preliminary study as "retail electricity suppliers and similar parties" and separately provides a preliminary consultation in which the customer, a licensed electrical contractor, or similar party discusses the service entrance location and the desired supply start date. Because the scope of who may apply differs by area, please check each company's guidance.

How long does it take to receive the response to a preliminary study?

Kansai Transmission and Distribution, Kyushu Electric Power Transmission and Distribution, and Tohoku Electric Power Network (extra-high voltage) state that, for whether construction is required and its type, the response is given within 2 weeks of acceptance as a rule. The detailed study, which also covers the construction period and an estimate of the construction cost contribution, takes around 3 months at Kansai Transmission and Distribution. Because in some cases the acceptance date is taken to be the day on which documents free of deficiencies are complete, eliminating deficiencies in the drawings and entries shortens the number of days until the response.

Related Articles and Services

References (Primary Sources)

* The content of this article is current as of its publication date. Later changes to rules or their operation may not be reflected, so please check the official announcements of each organization for the latest information. If you need your project checked against the latest rules, please feel free to contact us.

Reviewed by
General Manager, Energy Solutions Division, Grid Work Inc.

A licensed electrical engineer with more than ten years at a Japanese electric utility, working on substation design, construction and management. Draws on hands-on experience from the grid-operator side to support grid connection applications for power plants and grid-scale batteries, and to prepare application documents that avoid rejections.

How does this apply to your project?

Grid connection procedures differ by utility area and facility conditions. Questions at the “what would this mean for our case?” stage are welcome. Our team knows the utility-side process.