Data Center Grid Connection Application Support Supporting power receiving applications for high-voltage and extra-high-voltage (2,000kW and above) connections

Data center application support is a service that, on behalf of the operator, prepares and submits documents, responds to utility queries, and manages deadlines for preliminary studies and power receiving (wheeling supply) applications to electric utilities (general transmission and distribution utilities). A team that knows how utilities actually work supports power supply applications for high-voltage and extra-high-voltage data centers. We cover grid-side screening of candidate sites, the preliminary study, preparation of documents for the wheeling supply application via a retail electricity supplier, consultations with the utility, and deadline management after supply approval. We also welcome inquiries from overseas operators. You can consult us even before the receiving capacity (contracted power) has been determined. * The applicant for and party to the wheeling supply application is the retail electricity supplier. We support document preparation and consultations.

Last updated: November 17, 2026

(01) — Issue

Where data center electricity procedures tend to trip people up.

01

The procedure differs from power plant and battery applications

Because a data center is a demand facility that receives electricity, it follows the demand-side flow of a "preliminary study" and "wheeling supply application" rather than a connection study. The terminology, documents, and approach to costs differ from the generation side, so battery storage experience does not carry over directly.
02

Hard to read the grid situation at candidate sites

At extra-high voltage, some locations require years of utility-side facility reinforcement. Interpreting the Welcome Zone Map and preliminary study results and shortlisting candidate sites from a grid perspective requires an understanding of how the utility approaches its studies.
03

A missed deadline means lost capacity

From October 1, 2026, extra-high-voltage customers who do not pay the construction cost contribution (paid via the retail electricity supplier as the contracting party) within three months of supply approval will have the contract application for that site cancelled. For projects advancing multiple sites in parallel, centralized management of approval dates, payment deadlines, and desired supply start dates is essential.
(02) — Support

What We Cover for Data Center Power Supply Applications: From Preliminary Study to Supply Approval

We provide end-to-end support for the demand-side procedures, from the candidate site review stage through the start of supply.

01

Grid-side screening of candidate sites

We align the lot number, assumed contracted power, and desired supply start date for each site, cross-check them against each utility's Welcome Zone Map and Supply Availability Area Map, and organize which candidate sites should proceed to the preliminary study.
02

Support with preliminary consultation and preliminary study applications

For preliminary study applications made in your name or that of the retail electricity supplier, we support the preparation and submission of application documents in each utility's format, interpret the responses on whether construction is required, the estimated construction cost contribution, and the estimated construction period, and compile them into a comparison table of candidate sites. We handle parallel studies of multiple locations.
03

Preparation and consistency checking of wheeling supply application documents

We prepare the wheeling supply and basic contract application form, single-line diagram, list of receiving equipment, list of load equipment, supporting documentation for contracted power, and other documents, so that the application can proceed through the retail electricity supplier without risk of cancellation due to deficiencies or changes attributable to the customer.
04

Technical consultations and query responses with the utility

We organize the points to confirm in technical consultations and the approach to responding to queries and requests for additional materials, and, drawing on our understanding of how the utility conducts its review, we attend alongside and advise you and the retail electricity supplier.
05

Deadline and schedule management after supply approval

We track the supply approval date, the construction cost contribution payment deadline (three months), the desired supply start date, and the utility's construction period for each project and report at regular intervals. We also keep you informed of developments in the cost settlement rules for large-scale demand under consideration from FY2027 onward.
06

Centralized management of multiple sites

Even for projects advancing dozens of locations at once, we consolidate progress, queries, and deadlines for each utility into a single management sheet (our in-house progress management system) and share it with you.
(03) — Feature

Supporting high-voltage and extra-high-voltage supply applications from the standpoint of people who know how utilities work.

Team members with hands-on experience in substation design, construction, and management at a utility review the assessment of candidate sites and the content of application documents from the perspective of the utility's study and review process. Taking into account the differences between generation-side applications (solar and grid-scale battery storage) and demand-side applications (data centers), we design an approach suited to the nature of each project. As a group, we have supported more than 1,000 grid interconnection applications, of which approximately 150 were power supply applications for data centers (high voltage and extra-high voltage; approximately 100 high-voltage and approximately 50 extra-high-voltage). We handle everything from edge-type high-voltage projects to extra-high-voltage projects of several tens of MW.

* This service provides support with the preparation of application documents and advice on consultations; we do not become a party to the wheeling supply contract. We do not guarantee supply approval by the utility or the construction period or construction cost contribution. The track record figures are the cumulative number of grid interconnection and power supply application projects supported by our company and our group company (Virtual Work Inc.) (one supply point = one project, including low voltage) as of September 2026. Descriptions of rules and provisions are as of September 2026.

Procedure High Voltage Extra-High Voltage
Preliminary consultation and preliminary studyPRELIMINARY STUDY ✓ ✓
Wheeling supply application (support for applications via a retail electricity supplier)GRID SUPPLY APPLICATION ✓ ✓
Technical consultations and query responsesTECHNICAL CONSULTATION ✓ ✓
Deadline and schedule management after supply approvalDEADLINE MANAGEMENT ✓ ✓

Areas covered: general transmission and distribution utilities in all 10 areas of Japan Facilities covered: data centers (edge and hyperscale) and large-scale demand facilities The construction cost contribution payment deadline (three months after supply approval) and application cancellation rules effective October 1, 2026 apply to extra-high-voltage customers. * Where solar or battery storage for self-consumption is co-located, we also handle the generation-side grid interconnection application.

(04) — Capacity & Voltage

How to Proceed by Receiving Capacity and Voltage Class | High-Voltage, Extra-High-Voltage, and Undetermined Voltage

For a data center, the contracted power (receiving capacity) determines the voltage class, and the voltage class in turn determines the receiving equipment, the scale of the utility's construction work, and the weight of the procedures. Under TEPCO Power Grid's Wheeling Service Provisions, the standard voltage is 6,000V (high-voltage) for contracted power of 50kW or more and less than 2,000kW, 20,000V for 2,000kW or more and less than 10,000kW, 60,000V for 10,000kW or more and less than 50,000kW, and 140,000V for 50,000kW or more (all extra-high-voltage).

HV

High-Voltage (50kW or more, less than 2,000kW) Edge and in-building data centers

Power is received from a distribution substation or distribution line. When the project involves expanding existing receiving equipment or changing the voltage class, we prepare the supporting documents for the contracted power and the receiving equipment specifications before proceeding to the wheeling supply application. Because the construction period varies depending on overhead versus underground lines and whether excavation is required, we confirm the utility's estimates for each candidate site.
EHV

Extra-High-Voltage (2,000kW and above) Hyperscale and large-scale colocation

Power is received from a transmission line, and the receiving voltage (66kV, 154kV, etc.) and receiving method (dual-circuit supply, with or without a standby line) are determined through consultation with the general transmission and distribution utility responsible for the candidate site, based on its grid. Since building a new substation or reinforcing transmission lines can extend the utility's construction period to several years, we check the distance from candidate substations and the available capacity using the published supply potential map and welcome zone map, compare the need for construction, the estimated construction cost contribution, and the construction period through a preliminary study, and then proceed to the wheeling supply application.
TBD

When receiving capacity and voltage class are undetermined When only a list of candidate sites exists

We set a range of contracted power (e.g., 2MW, 10MW, 30MW) based on the expected IT load and perform an initial screening of the expected voltage class and the grid conditions at the candidate sites for each range. For plans with phased commencement of supply, we organize the contracted power and desired supply start date for each phase and finalize the application details so that they do not conflict with the application cancellation rules effective October 1, 2026 (changes for the customer's own reasons before supply approval, and the three-month payment deadline for the construction cost contribution). For projects near the voltage class boundary (around 2,000kW), we consult with the utility early, taking into account receiving equipment costs and room for future expansion.

* The standard voltage classes shown are examples from TEPCO Power Grid's Wheeling Service Provisions (effective October 1, 2026). The classes and receiving voltages of other general transmission and distribution utilities should be confirmed in each company's provisions and published materials. Depending on special circumstances or the condition of supply facilities, power may be supplied at a voltage above or below the standard voltage.

(05) — Flow

How Data Center Application Support Works: From Inquiry to Start of Supply

We advance each stage of the demand-side procedure in step with your development schedule.

01

Consultation and sharing of the candidate site list

We ask for the location of each candidate site (address and lot number), assumed contracted power, desired supply start date, and development schedule. We proceed under a non-disclosure agreement.
02

Grid-side screening

Based on the published maps and our practical knowledge, we organize the candidate sites from a grid perspective and propose which locations should proceed to the preliminary study.
03

Preliminary study application and analysis of responses

We support the preliminary study application made in your name or that of the retail electricity supplier, and deliver the responses on whether construction is required, the estimated construction cost contribution, and the estimated construction period in a comparison table.
04

Wheeling supply application and consultations

We prepare the documents needed for the wheeling supply application via the retail electricity supplier and handle technical consultations and queries. We report progress toward supply approval at regular intervals.
05

Deadline and schedule management after approval

We manage the construction cost contribution payment deadline and the desired supply start date, and support you through to the start of supply while confirming that the utility's construction work and your own construction schedule remain aligned.

* Timelines and team structure vary by project. Indicative utility study periods are: Kansai Transmission and Distribution, within two weeks for whether construction is required and around three months for the detailed study; Chubu Electric Power Grid, normally 30 business days or more (per each company's published materials). Selection of and contracting with a retail electricity supplier is handled with the relevant companies, and administrative procedures associated with the development (permits and approvals, etc.) with our partner licensed administrative scriveners.

(06) — Global

For Overseas Operators and Investors

Data Center Grid Connection in Japan — In Japanese data center development, application forms, technical consultations, and query responses with the utility are normally conducted in Japanese, and the retail electricity supplier that becomes party to the wheeling supply contract is also a Japanese company. Grid Work accepts initial consultations with overseas development teams and investors (by email) in English, Chinese (Simplified and Traditional), and Korean, and supports the procedures with Japanese utilities in Japanese. Please consult us about the language of regular reports for each project. An overview of the Japanese system is provided in our Q&A for overseas operators. This service overview in other languages: 日本語 / English / 简体中文 / 繁體中文 / 한국어
(07) — FAQ

Frequently Asked Questions

Does a data center also need a connection study?
If it is a demand facility with no co-located generation equipment and no reverse power flow, the generation-side connection study does not apply. We proceed through the demand-side flow of preliminary study and wheeling supply application.
We have dozens of candidate sites. Can they be advanced in parallel?
Yes, we handle parallel studies of multiple locations. However, in consideration of the utilities' study workload, we first carry out a first screening using the published maps and then narrow down the locations that proceed to the preliminary study. If you provide the location (address and lot number) and assumed contracted power for each site, we return the results in the form of a comparison table.
How are fees determined?
We quote individually based on three factors: the scope of the procedure (preliminary study only, through the wheeling supply application, or support through the start of supply), the number of locations, and the voltage class (high voltage or extra-high voltage). Please feel free to contact us through the inquiry form even at the information-gathering stage, before any formal review.
Which areas do you cover?
We cover the general transmission and distribution utilities in all 10 areas of Japan. We handle the differences in forms and procedures between utilities on our side.
What changes for extra-high-voltage applications from October 2026?
Payment of the construction cost contribution within three months of supply approval becomes a deadline; if it is exceeded, the contract application for that site is cancelled. Deficiencies or changes attributable to the customer also result in cancellation and resubmission of the application. We track the approval date and payment deadline for each project.
Can we engage you for an edge data center (high-voltage supply)?
Yes. High-voltage supply applications involve shorter utility-side construction periods than extra-high voltage (Kansai Transmission and Distribution's indicative figures are around 3 to 5 months for overhead lines and 3 to 9 months for underground lines), making them well suited to rolling out multiple sites at the same time.
How is a data center's receiving voltage determined?
Under TEPCO Power Grid's Wheeling Service Provisions (as of October 2026), the standard voltages are low-voltage at 100V and 200V, high-voltage at 6,000V, and extra-high-voltage at 20,000V or above. As a guide by contracted power, 50kW or more and less than 2,000kW is 6,000V (high-voltage), 2,000kW or more and less than 10,000kW is 20,000V, 10,000kW or more and less than 50,000kW is 60,000V, and 50,000kW or more is 140,000V (all extra-high-voltage). Power may be supplied at a higher or lower voltage depending on special circumstances or the condition of supply facilities, and other utilities use different classes, so confirmation with the utility is required for each candidate site. We can advise you on how to proceed with these confirmations for each candidate site.
Our receiving capacity (contracted power) has not been decided yet. Can we still consult you?
Yes. We set a range of contracted power (e.g., 2MW, 10MW, 30MW) based on the expected IT load and perform an initial screening of the expected voltage class and the grid conditions at the candidate sites (distance from candidate substations, available capacity, and published maps) for each range. For plans with phased commencement of supply, we organize the contracted power and desired supply start date for each phase and work with you to finalize application details that do not conflict with the application cancellation rules.
If the contracted power is around 2,000kW, should we apply as high-voltage or extra-high-voltage?
Under the standard voltages in TEPCO Power Grid's provisions, 2,000kW or more falls on the 20,000V (extra-high-voltage) side. However, there is an exception allowing supply at a voltage above or below the standard voltage due to special circumstances or the condition of supply facilities, and the choice also affects receiving equipment costs and room for future expansion, so for projects close to the boundary we consult with the utility at the preliminary consultation stage. We help you organize the materials for comparing the two options (receiving equipment, construction period, and the estimated construction cost contribution).

This FAQ summarizes general information based on materials published by the national government and each general transmission and distribution utility as of November 2026. Actual handling may differ depending on the utility and the conditions of each project. Because systems and operational practices are subject to change, please check each company's published materials for the latest information.