When a Data Center Preliminary Study Comes Back with “No Available Supply Capacity” or “Construction Period Over 10 Years”: How to Read the Response and What Options Come Next
The main reason a data center preliminary study comes back with a long construction period is that work on the upstream grid is required, such as a new substation, an additional transformer, or a new transmission line. According to materials published by TEPCO Power Grid, the standard construction period for extra-high-voltage (66 kV and above) work involving a new substation or an additional transformer is about 120 months. Once you receive the response, compare side by side a revision of the receiving capacity, phased power receiving, replacement of the candidate site, reconsideration of the voltage class, and a revision of the desired supply start date. This article is for developers and investors who have received a response, and sets out how to read the response and the options that come next, to the extent that can be confirmed in materials published by the general transmission and distribution utilities and the national government.
This article is based on materials published as of November 17, 2026. Rules and application forms may be revised, so before proceeding, please also check the latest materials published by the relevant general transmission and distribution utility and other authorities.
What Does the Preliminary Study Response Say?
What the response to a preliminary study tells you is, basically, "whether construction is required" and "the type of work if construction is required." If you also want to know the construction period and an estimate of the construction cost contribution, you confirm these through a detailed study or a preliminary consultation. How far the response goes depends on the type of procedure you applied for.
Kansai Transmission and Distribution presents the supply-side preliminary connection study and the detailed study separately. The supply-side preliminary connection study indicates whether construction is required and the type of work (access facility work, electricity meter work, or communication facility work). In the detailed study, the response covers an outline of the work, the required construction period, an estimate of the construction cost contribution, the conditions of supply, and so on. TEPCO Power Grid likewise explains the preliminary study, on its high-voltage procedures page, as a procedure for cases where a retail electricity supplier or similar party wishes to confirm "whether construction is required" and "the type of work if construction is required" ahead of the contract application. Its document on standard construction periods for extra-high-voltage (66 kV and above) work directs applicants to confirm the construction period for a specific point by requesting a preliminary consultation.
Item
Supply-side preliminary connection study
Detailed study
Content of the response
Whether construction is required and, if so, the type of work
An outline of the work, the required construction period, an estimate of the construction cost contribution, the conditions of supply, and so on
Period until the response
Within 2 weeks of receiving the application as a rule
Around 3 months from receiving the application
Position
Optional procedure (not mandatory)
Reflects the position at the time of the response and does not guarantee future available supply capacity
The table above reflects what is stated on Kansai Transmission and Distribution's official page. As for the response form itself, the "supply-side preliminary connection study application form" and the "preliminary study response form" are included in the list of forms of the Organization for Cross-regional Coordination of Transmission Operators (OCCTO). The overall flow of the procedures is also explained in our article explaining the supply-side preliminary connection study and in The Data Center Grid Connection (Power Supply) Application Flow.
The Response Is Not Final
Kansai Transmission and Distribution states that the response to the detailed study reflects the position at the time of the response and is guaranteed by supply approval (the result of the supply study after the contract application). It also states that the content of the response may change. Read the construction period in the response as "an estimate premised on the grid conditions at that point in time."
When you receive the response, checking the following points exactly as worded makes later comparison easier.
Whether construction is required and the type of work (which facilities the work concerns)
The starting point of the construction period (from the application, or from payment of the construction cost contribution)
The contracted power, receiving voltage, receiving method, and desired supply start date that were assumed
The statement that the construction period and amounts are approximate, and the assumptions behind them
Types of Work That Lengthen the Construction Period, and Standard Construction Periods
The construction period reaches the order of 10 years where a new substation or an additional transformer is required. Even a new transmission line alone has a standard period of about 42 months for an overhead line and about 96 months for an underground line. In "Standard construction periods for extra-high-voltage (66 kV and above) work" (May 2026), TEPCO Power Grid publishes the standard construction period for each type of work.
Supply method
Content of the work
Standard construction period
Overhead transmission line
New substation or additional transformer, plus new or rebuilt steel towers (fewer than 3 towers, about 0.7 km)
About 120 months
Overhead transmission line
New or rebuilt steel towers (fewer than 3 towers, about 0.7 km)
About 42 months
Overhead transmission line
Renewal of receiving equipment (removal and replacement of the overhead service line)
About 24 months
Underground transmission line
New substation or additional transformer, plus new conduits and cables (about 3 km)
About 120 months
Underground transmission line
New conduits and cables (about 3 km)
About 96 months
Underground transmission line
Renewal of receiving equipment (removal and replacement of cables)
About 30 months
This table shows standard values with 2 circuits and a receiving voltage of 66 kV to 154 kV as common conditions. The construction period is the period from application to energization, and is shown as the construction period once the construction plan has been finalized, on the premise that the location and specifications of the receiving equipment have been finalized. The figure of about 120 months is the standard value for construction of a new 154 kV substation and is stated to vary greatly with the voltage level and the number of transformers.
Assumptions Behind the Standard Construction Periods and Factors That Change Them
The document expressly states that the construction periods shown are approximate and do not guarantee supply within the period. The condition of existing facilities, local conditions such as roads, rivers, and buried objects, and constraints on land acquisition are not taken into account. The main factors cited for variation are securing the transmission route, permits and approvals, the local environment, coordination of facility outages, land negotiations, and longer material procurement times. The construction period for a specific point can be confirmed through a preliminary consultation, and as a result of the detailed study it may differ greatly from the periods in the table.
Kansai Transmission and Distribution does not give a uniform period for extra-high-voltage supply construction. Because it varies greatly with material procurement, applications and permits, whether there is a construction cost contribution, and other factors, each application is subject to individual consultation. In the preliminary studies we have handled as well, we sometimes receive responses with a construction period exceeding 10 years and responses stating that there is no available supply capacity. This is our own practical experience and is separate from the published figures above.
What Does "No Available Supply Capacity" Mean? The Relationship with the Published Maps
A definition of the response "no available supply capacity" is not given within the published materials we checked. What can be read from the explanations of the published maps is the following relationship: available supply capacity (available capacity) is a guide to the demand that existing facilities can accommodate, and where the available capacity is exceeded, reinforcement work such as an additional transformer becomes necessary. Confirm with the general transmission and distribution utility which facility's available capacity the wording of the response refers to.
Under the approach Kansai Transmission and Distribution set out in its document introducing the map (dated March 1, 2024; the map is as of November 2023), large-scale development exceeding the available capacity on the map requires large-scale reinforcement such as an additional transformer, with a construction period of 5 years or more as a guide. Even so, it may be possible to secure supply capacity of around 100 to 300 MW, and the supply method, construction period, and construction cost are stated to be matters for individual consultation. In other words, a response that there is no available capacity does not necessarily mean "supply is not possible"; in some cases it means "it will take time on the premise of reinforcement work." The starting point is to confirm which of the two is meant.
Item
TEPCO Power Grid
Kansai Transmission and Distribution
Main published maps
Welcome Zone Map (for those seeking extra-high-voltage supply at 2,000 kW or more), Large-Scale Supply Potential Map
Welcome Zone Map (high voltage and extra-high voltage), Supply Availability Area Map (for large-scale supply of tens to hundreds of MW)
Scope of the map for large-scale demand
Substations with available capacity of 50 MW or more at a receiving voltage of 154 kV or 66 kV, and substations with available capacity of 400 MW or more at 275 kV
Customers at a standard voltage of 70 kV with contracted power of 10,000 kW or more. The large-scale version shows available supply capacity of around 100 to 300 MW, and the small-to-medium-scale version around 10 to 50 MW
How the construction period is shown
Approximate construction period of around 5 years (within a range of about 1 to 1.5 km around the substation) and around 10 years (within a range of about 5 to 6 km)
Shown in years for each substation. The detailed version covers areas with available capacity of 10 MW or more and a construction period of around 3 to 5 years. The construction period is the period from payment of the construction cost contribution to the start of transmission
As-of date
The Large-Scale Supply Potential Map was prepared on October 30, 2026. Available supply capacity for the whole area is as of December 2025
The Supply Availability Area Map is as of September 2026
Why the Map and the Response Sometimes Differ
Even in an area shown on the map as having available capacity, the response may state that there is none. Both companies expressly state that the figures on the maps are a guide. TEPCO Power Grid states that available capacity may change with other applications and changes in grid conditions, and its map of available supply capacity also notes that grid reinforcement work may become necessary. Kansai Transmission and Distribution likewise states that the construction period and available capacity are a guide and may change in the detailed study at the time of application.
Conversely, an area not shown on the map cannot necessarily be said to be unable to receive supply. Kansai Transmission and Distribution states that the published scope is updated from time to time and that supply may be possible even in unpublished areas, and directs applicants in that case to apply for a preliminary study. The differences between each company's maps are summarized in our guide to the Welcome Zone Maps by general transmission and distribution utility.
How to Compare the Options After Receiving the Response
The options after the response divide into ways of changing the conditions at the same site (receiving capacity, phased power receiving, voltage class, and desired supply start date) and a way of changing the site itself (replacing the candidate site). Which is effective depends on which work the response identifies as the cause of the long period. Because the construction period under changed conditions cannot be calculated from the published materials, in every case it is confirmed through another preliminary study or consultation with the general transmission and distribution utility.
Option
Effect that can be expected
Points to note
Lower the receiving capacity
If it fits within the available capacity of existing facilities, the work may fall into a type that does not involve a new substation or an additional transformer
What capacity would fit is not published. Confirm by changing the conditions and applying for a preliminary study again. A matter for consultation with the general transmission and distribution utility
Receive power in phases
Under a phased contract, contracted power can be set by year in line with the start of operation
The Agency for Natural Resources and Energy's materials explain that this is premised on facilities for the final scale being built in advance. Whether the construction period becomes shorter where reinforcement of the upstream grid is required is a matter for individual consultation
Replace the candidate site
You can choose the supply range of a different substation after checking the indicative available capacity and construction period on the published maps
The maps are a guide and may change in the study at the time of application. Conditions such as land acquisition are also subject to review together
Reconsider the voltage class
If the receiving voltage changes, the facilities connected to and the work required change
The receiving voltage is determined by the Wheeling Service Provisions according to contracted power and also differs by location. It cannot be chosen freely and is a matter for consultation with the general transmission and distribution utility
Revise the desired supply start date
The business plan can be reworked to match the construction period in the response
The construction period itself does not become shorter. At TEPCO Power Grid, since October 1, 2026, the contract application is cancelled if the application details change for the customer's own reasons before supply approval. A review of the discipline on changes after supply approval is under discussion
Receiving Capacity and Voltage Class
TEPCO Power Grid's Welcome Zone Map is for those seeking extra-high-voltage supply at 2,000 kW or more. Kansai Transmission and Distribution's Supply Availability Area Map provides information for customers at a standard voltage of 70 kV with contracted power of 10,000 kW or more. One approach is to lower the capacity so that it falls within the high-voltage range, but in that case the scale of the facility itself changes. The boundary between high voltage and extra-high voltage is set out in Data Center Receiving Capacity and Extra-High-Voltage Supply (Japanese), and the approach to receiving power at high voltage in our guide to high-voltage data centers.
Phased Power Receiving
The Agency for Natural Resources and Energy's materials explain that where operation starts in phases, a phased contract is concluded. As an example, they show a case in which 100 MW is set for 2028, 200 MW for 2030, and 300 MW for 2032. According to the materials, because facilities for the final scale are built in advance under a phased contract, it is used from the standpoint of efficiency and of meeting the desired supply date. Phased power receiving is a means of deciding how capacity is ramped up. Where the cause of the construction period in the response lies in reinforcement of the upstream grid, whether the initial phase alone can receive power early cannot be confirmed from the published materials. It is a matter for consultation with the general transmission and distribution utility.
Replacing the Candidate Site
When replacing a candidate site, check the indicative figures on the maps before proceeding to a preliminary study. As a way of using the map when the site has not been decided, Kansai Transmission and Distribution sets out a flow of checking the supply availability area on the map, applying for a wheeling supply contract if the site is within the area, and searching for other sites if it is outside the area. TEPCO Power Grid's Large-Scale Supply Potential Map divides the approximate construction period into around 5 years and around 10 years according to the distance from the substation. It can be read from this that the distance from the substation affects the construction period. For the items to check at the stage of searching for land, see our Power Checklist for Data Center Site Selection.
The National Discussion and Future Rules
For localized large-scale demand, the national government has been considering 3 points: procedural discipline, the allocation of costs for reinforcing the upstream grid, and making maximum use of existing facilities. TEPCO Power Grid applied for approval of changes to its Wheeling Service Provisions on June 24, 2026 and received approval on July 22. Since October 1, 2026, it has implemented the treatment of cancelling the contract application where the application details change for the customer's own reasons before supply approval. The release of capacity and changes to contracted power after supply approval are being discussed in the national working group. Here we set out what can be confirmed in the Agency for Natural Resources and Energy's Next-Generation Power Grid Working Group document "Ensuring discipline for localized large-scale demand" (April 16, 2026).
The document points out that "speculative capacity reservation," in which only part of the grid capacity that has been secured is used, is occurring. It states that in areas with speculative capacity reservation, additional facilities need to be built, and that in some regions a vicious cycle has arisen of longer connection periods due to queuing and an increase in early applications. In some regions, circumstances of this kind may lie behind a response with a long construction period.
Issue
Content set out in the document
Status
Stalling at the technical study stage
Where there are deficiencies or changes attributable to the customer, the contract application is cancelled. Minor changes that do not affect the result of the technical study are permitted
A proposed measure as of April 16, 2026. Since October 1, 2026, TEPCO Power Grid has implemented the treatment of cancelling the contract application where the application details change for the customer's own reasons before supply approval
Measure ① (release of capacity)
In areas with many connection applications, where the start of supply is postponed or contracted power is reduced partway through a phased contract, make it possible to release the difference in grid capacity to projects waiting for connection. A postponement of only 1 year and the like is stated to be within the permitted range
A proposal as of April 16, 2026. The scope of the areas covered and other matters to be considered at subsequent meetings
Measure ② (change of contracted power and settlement)
Where the final contracted power in the original plan is not reached for a certain period, make it possible for the general transmission and distribution utility to change the contracted power. Settlement of actual costs arises under the provisions
A proposal as of April 16, 2026. The length of the "certain period" to be discussed at subsequent meetings
In the materials as of April 16, 2026, Measures ① and ② are proposals covering large-scale demand at or above a certain scale, and the criteria are to be considered at subsequent meetings. No specific schedule is stated in that document. According to the summary of proceedings of the 11th Working Group meeting on June 10, 2026, matters such as the scale to be covered continue to be discussed. The April 16, 2026 document explains that the current Wheeling Service Provisions also provide that where, after part or all of the supply facilities have been installed, a contract is terminated or changed without supply having started for reasons of the contracting party or the customer, the actual costs incurred are collected from the contracting party. The rules on cancellation after the contract application are covered in Data Center Supply Start Dates and Application Cancellation Rules.
The Study Group of the Electricity and Gas Market Surveillance Commission
The Electricity and Gas Market Surveillance Commission established the "Study Group on Localized Increases in Electricity Demand and the Transmission and Distribution Network" in March 2024 and published its compiled report on June 11, 2024. According to the publication page, because facility reinforcement takes a long time and involves large costs, planned facility reinforcement and efficient use of the existing network are important. It set out 5 issues for deeper consideration going forward: the wheeling charge system, control of resources, guiding demand to locations where prompt connection is possible, planned development of the transmission and distribution network, and mitigating the impact of connecting new demand. It is stated that these are expected to be considered, including whether they should be implemented at all, at expert meetings and similar forums.
Items to Organize When Explaining to Internal Stakeholders and Investors
When explaining internally or to investors, present separately the facts in the response, the cross-check against published materials, and the next procedure for each option. It is important not to mix the figures in the response with your own interpretation. Summarizing the following items on 1 page aligns the premises for the decision.
The type and date of the response (supply-side preliminary connection study, detailed study, or preliminary consultation)
The assumptions behind the response (contracted power, receiving voltage, receiving method, number of circuits, and desired supply start date)
Whether construction is required and the type of work, and the starting point of the construction period
The result of the cross-check against published materials (which type in the standard construction periods it is closest to, and the indicative available capacity and construction period on the map)
That the response is not final (it is guaranteed by supply approval, and the content of the response may change)
The next procedure for each option and the period until its response (for example, around 3 months for the detailed study)
Undetermined matters concerning costs (whether there is an estimate of the construction cost contribution, and settlement of actual costs if the contract is changed or terminated after the supply facilities have been installed and before the start of supply)
The risk of rule changes (the proposals under national discussion for releasing capacity and changing contracted power)
Kansai Transmission and Distribution asks applicants to refrain from applications that are not backed by an actual business and are aimed only at securing available supply capacity, and states that it may ask for a business plan to be submitted or explained before accepting a contract application. Even when studies are being advanced for multiple candidate sites, the premise is that you are in a position to explain the business plan for each one. We also assist with reading the response and structuring the next application through our Data Center Grid Connection Application Support. Fees are quoted individually according to the number of sites, the voltage class, and the scope of work.
Frequently Asked Questions About Preliminary Study Responses
Can the construction period given in the response be shortened?
Within the published materials, we could not find a procedure for shortening the construction period. TEPCO Power Grid states that the standard construction periods are approximate and vary with securing the transmission route, permits and approvals, land negotiations, material procurement, and other factors. Kansai Transmission and Distribution states, in its guidance for high-voltage customers, that the dates for obtaining the various applications and construction permits cannot be shortened. The construction period may be changeable where assumptions such as the receiving capacity or the candidate site are changed and the type of work required changes as a result. The outcome is confirmed through another preliminary study or consultation.
Does the response to a preliminary study have an expiry date?
The official pages of TEPCO Power Grid and Kansai Transmission and Distribution that we checked did not state an expiry date for the response to a preliminary study. On the other hand, Kansai Transmission and Distribution expressly states that the response to the detailed study reflects the position at the time of the response and does not guarantee future available supply capacity. As time passes after the response, grid conditions may change because of other applications. Judge whether there is an expiry date and how it is treated from what is stated in the response and by confirming with the general transmission and distribution utility.
Should we resubmit a preliminary study in a different area?
Where the cause of the long period lies in a new substation or an additional transformer, it is worth considering a different candidate site in parallel. First check the indicative available supply capacity and construction period on each company's published maps, narrow down the candidates, and then apply for a preliminary study. However, the figures on the maps are a guide and may change in the study at the time of application. Because applicants are asked to refrain from applications aimed only at securing available supply capacity, the premise is to apply only for sites for which you can explain the business plan.
On what basis do we decide whether to proceed to the formal application (contract application)?
One criterion is whether you can finalize the application details, such as contracted power, the power receiving point, and the desired supply start date. Since October 1, 2026, TEPCO Power Grid has implemented the treatment of cancelling the contract application where the application details change for the customer's own reasons before supply approval. The Agency for Natural Resources and Energy's materials explain that under the current provisions too, settlement of actual costs arises if, after part or all of the supply facilities have been installed, a contract is terminated or changed without supply having started for reasons of the contracting party or the customer. We recommend confirming whether the business is viable with the construction period given in the response and proceeding once the details are settled.
* The content of this article is current as of its publication date. Later changes to rules or their operation may not be reflected, so please check the official announcements of each organization for the latest information. If you need your project checked against the latest rules, please feel free to contact us.
Reviewed by
General Manager, Energy Solutions Division, Grid Work Inc.
A licensed electrical engineer with more than ten years at a Japanese electric utility, working on substation design, construction and management. Draws on hands-on experience from the grid-operator side to support grid connection applications for power plants and grid-scale batteries, and to prepare application documents that avoid rejections.
How does this apply to your project?
Grid connection procedures differ by utility area and facility conditions. Questions at the “what would this mean for our case?” stage are welcome. Our team knows the utility-side process.