Column

How to Read the Welcome Zone Map (Available Supply Capacity Map): A Utility-by-Utility List for Data Centers

The Welcome Zone Map (available supply capacity map) is published material in which a general transmission and distribution utility shows the areas and substations where it may be able to supply electricity relatively quickly to large-scale demand such as data centers and factories. It is used for a first screening of candidate sites, and being shown on the map does not mean that supply is guaranteed. Whether power can be received at a specific site, and when and at what cost, is confirmed through a preliminary study (preliminary consultation) with the general transmission and distribution utility. This article is for developers and real estate professionals and investors looking for candidate sites for data centers, and summarizes what we were able to confirm in the council materials of the Agency for Natural Resources and Energy and on each company's official pages.

This article is based on materials published as of November 17, 2026. Rules and application forms may be revised, so before proceeding, please also check the latest materials published by the relevant general transmission and distribution utility and other authorities.

What Is the Welcome Zone Map?

"Welcome Zone Map" is a collective term for the maps and materials in which general transmission and distribution utilities show "places where electricity supply can begin early." The Agency for Natural Resources and Energy's council document "Responding to the Siting of Localized Large-Scale Demand" (January 23, 2025) explains it, as a description in the (draft) 7th Strategic Energy Plan, as something in which general transmission and distribution utilities show places where electricity supply can begin early. In light of localized demand siting such as data centers, it is positioned as a near-term measure for making efficient use of the grid facilities that exist today. The name differs from company to company. In addition to "Welcome Zone Map," the materials are published under names such as "Available Supply Capacity Map," "Supply Availability Area Map," "Large-Scale Supply Potential Map," and "Early Supply Availability Area Map for Large-Scale Demand." When searching, looking for these names together makes the materials easier to find.

How It Has Been Treated in the National Discussion

According to the same document, at the 51st meeting of the Grid Working Group on May 24, 2024, it was decided that utilities that had not published a map would also consider doing so, including whether coordination with local governments and others was needed, and would prepare one early, aiming for around FY2024, to the extent that could be published. Utilities that had already published a map were asked to consider whether they could publish additional information, such as the distance to power facilities and the size of land plots. The document dated June 27, 2025, "Ensuring discipline for localized large-scale demand," states that efforts had been advanced to publish the maps within FY2024 and that going forward it is important to expand them in light of customers' needs and to take information disclosure further. It also notes that the summary report of the Public-Private Council on Watt-Bit Collaboration set out a policy of encouraging data centers to locate in areas with available grid capacity through expansion of the maps and other means. The document of the same name dated April 16, 2026 lists "information disclosure through the Welcome Zone Map" as one of the efforts to make maximum use of existing facilities. The same document also touches on "speculative capacity reservation," in which only part of the grid capacity that has been secured is used, and on the problem of longer periods until connection. The maps are an information disclosure effort being advanced alongside the responses to these problems. The discipline that applies after the application is set out in Data Center Supply Start Dates and Application Cancellation Rules. In addition, the website of the Electricity and Gas Market Surveillance Commission carries a document (dated March 1, 2024) in which Kansai Transmission and Distribution introduced its own map. This document explains the purpose of publication as enabling users to check the indicative available supply capacity and construction period for themselves, where previously they had to wait for the response to a preliminary study.

What the Map Tells You and What It Does Not

What the map tells you is a rough outlook: "around which substations and transmission lines there is roughly how much available supply capacity, and roughly what construction period is indicated." On the other hand, it does not tell you whether power can be received at a specific site, the actual construction period, or the amount of the construction cost contribution. Every company notes that the figures shown are a guide and change in a detailed study.
Item What the map tells you What the map does not tell you
Available supply capacity Indicative available supply capacity for each substation or transmission line (bands or approximate figures) The actual available capacity at the time of application. It changes with other applications and grid conditions
Location The approximate location of substations and transmission lines with available capacity, and the surrounding area The transmission line route to a specific site, and land and road constraints
Construction period Indicative periods such as "around 3 to 5 years" or "around 5 years" (the definition differs by company) The actual construction period reflecting land negotiations, permits and approvals, material procurement, and so on
Receiving voltage The voltages covered (66 kV, 154 kV, etc.) The voltage and number of circuits ultimately applied to your contracted power and site
Cost At some companies, the approach to the construction cost contribution and example approximate calculations The amount of the construction cost contribution for a specific project
Whether power can be received A clue as to whether the site is worth considering as a candidate A guarantee of supply. This is decided in the preliminary study and the detailed study after the application
For example, TEPCO Power Grid notes that available supply capacity may vary with grid conditions, supply to new customers, and other factors. Kansai Transmission and Distribution states that the construction period and available capacity are a guide and may change in the detailed study at the time of application. Tohoku Electric Power Network likewise expressly states that the suppliable capacity, required construction period, and supply method are a guide and may be changed by the study result for the "supply-side preliminary connection study application form." The starting point of the construction period also needs attention. In Kansai Transmission and Distribution's materials, the construction period is the period from receipt of the "wheeling supply and basic contract application form," through payment of the construction cost contribution, to the start of transmission. In Tohoku Electric Power Network's materials, the indicative construction period is the period from the start of construction and does not include the period for procedures before that. The same "4 years" means something different if the starting point differs.

Publication Status by General Transmission and Distribution Utility

When we checked each company's official pages as of November 17, 2026, we were able to confirm that 9 of the 10 companies carry a Welcome Zone Map or equivalent material. Okinawa Electric Power also has a "Welcome Zone Map" page on its official website, but because we had not been able to check its content as of November 17, 2026, we have not given details. The way the scale covered and the as-of date are written differs from company to company. The table below summarizes only the statements we were able to confirm in the body of each company's pages and materials.
Company Name of material Scale and voltage covered (as stated in the source) As-of date and update date (as stated in the source) URL
Hokkaido Electric Power Network Map for Connecting to Electricity (presents power grid information (Welcome Zone Map) on a map) Available supply capacity covers extra-high-voltage power. Indicative connectable capacity is shown in MW bands The grid diagram is as of May 2026; available supply capacity is under the conditions assumed as of December 2025 Official page
Tohoku Electric Power Network Guide to Welcome Zones (candidate supply points for large-scale demand) Large-scale supply of around 50,000 to 300,000 kW. Supply at a standard voltage of 140 kV is the basic approach. Points that can be handled relatively early (around 3 to 5 years) The outline study is as of February 2026 Official document (PDF)
TEPCO Power Grid Welcome Zone Map / Large-Scale Supply Potential Map For customers seeking extra-high-voltage supply at 2,000 kW or more. Available supply capacity is for 66 kV and 154 kV. For 50,000 kW or more, the Large-Scale Supply Potential Map The map is as of December 2025. The Potential Map was prepared on October 30, 2026 Official page
Chubu Electric Power Grid Welcome Zone Map of the Chubu Region For companies considering new factories and the like that receive supply at extra-high voltage. Checked on maps by prefecture Published March 28, 2025 (an expansion of the "Available Supply Capacity Map of the Chubu Region" launched on September 18, 2024). We could not find a statement of the update date Official page
Hokuriku Electric Power Transmission and Distribution Corporate Sites and Welcome Zones in the Hokuriku Region (Early Supply Availability Area Map for Large-Scale Demand) The pages by prefecture (checked for Ishikawa Prefecture) list facilities with available supply capacity of 50 MW or more. We could not find a statement of the voltage We could not find a statement of the as-of date Official page
Kansai Transmission and Distribution Welcome Zone Map / Supply Availability Area Map and Contribution and Construction Period Quick-Reference Map For customers seeking high-voltage or extra-high-voltage supply. The Supply Availability Area Map covers a standard voltage of 70 kV and contracted power of 10,000 kW or more The Supply Availability Area Map is as of September 2026 (posted October 21, 2026) Official page
Chugoku Electric Power Transmission and Distribution Available Supply Capacity Map (within the Welcome Zone Map) Available supply capacity information for 19 substations at 110 kV, 21 substations at 66 kV, and transmission facilities by prefecture Stated only as "at present." We could not find a date Official page
Shikoku Electric Power Transmission and Distribution Welcome Zone Map (information for businesses considering the siting of large-scale demand and the like) Mainly for customers seeking supply at extra-high voltage. Supply voltages of 66 kV (by prefecture) and 187 kV As of October 15, 2026 Official page
Kyushu Electric Power Transmission and Distribution Welcome Zone Map (Kyushu industrial site information / Available Supply Capacity Map) We could not find a statement of the voltage or scale covered in the body of the page (it is shown in map images) We could not find a statement of the as-of date in the body of the page (please check what is shown in the map images) Official page
Okinawa Electric Power Please check the official page Please check the official page Please check the official page Please check the official page

Notes on the Table

Tohoku Electric Power Network's document lists candidate points in Akita, Miyagi, and Niigata Prefectures with the substation names. Indicative suppliable capacity is in 3 bands: 300,000 kW, 100,000 kW, and 50,000 kW. The maps for Aomori, Iwate, Yamagata, and Fukushima Prefectures carry a note that grid reinforcement work is expected to be necessary. For points not listed, or where a larger supply is desired, the guidance is to inquire individually. Hokuriku Electric Power Transmission and Distribution lists the supply capacity and shortest construction period for each substation and transmission line on pages by prefecture. On the Ishikawa Prefecture page, for 4 substations and 7 transmission lines, the supply capacity is given as 50 MW to 300 MW and the shortest construction period as around 4 and a half years in every case. It is noted that the shortest construction period applies where the supply point is located near the company's facilities, and that the construction period becomes longer further from the facilities. Shikoku Electric Power Transmission and Distribution states that supply can be expected in roughly 5 years or so if the site is within about 3 km of a substation or transmission line. It also states that where contracted power exceeds 50,000 kW, interconnection at 187 kV may be discussed. Chugoku Electric Power Transmission and Distribution states that supply above the published available supply capacity may become possible through grid reinforcement with a relatively short construction period, and directs customers to consult its contact point first. Hokkaido Electric Power Network's map carries a note that, for the 187 kV grid, it shows available supply capacity from December 2029 onward. Early inquiry is recommended for those seeking contracted power exceeding 10 MW. For the differences between each company's application contact points, see also Grid Interconnection Application Contact Points and Differences Among the 10 General Transmission and Distribution Utilities (Japanese).

How to Read TEPCO Power Grid's Maps

TEPCO Power Grid's Welcome Zone Map is a page for customers seeking extra-high-voltage supply at 2,000 kW or more. In addition to "Search by industrial park" and "Search by available supply capacity," it has a "Search by conditions" entry point for narrowing down by conditions such as area and construction period. Those seeking extra-high-voltage supply of 50,000 kW or more are directed to look separately at the "Large-Scale Supply Potential Map" (PDF).

Search by Available Supply Capacity (66 kV and 154 kV)

On the available supply capacity page, you can view maps in "graduated display" and "heat map display" for each of 66 kV and 154 kV. The information is as of December 2025. Because the legend is shown as an image, please check the correspondence between colors and available capacity on the official page. The notes state the following points. The map is for customers, and generators should refer to the separate "Available Capacity Map." Available supply capacity may vary with grid conditions, supply to new customers, and other factors. Depending on the contracted power and the supply point, the supply voltage may be 66 kV or 154 kV. Available capacity on the generation side and available supply capacity on the demand side are different information, so take care not to confuse them. The pages by prefecture (which show industrial parks and available supply capacity together; information as of December 2025) also carry a note on the construction period. The construction period until supply is stated to be the period from the application, following the preliminary consultation (which may take 1 year or more). It also states that where interconnection is desired at contracted power above the available supply capacity, countermeasure work at the source substation or elsewhere becomes necessary and the construction period is highly likely to become longer.

Large-Scale Supply Potential Map (50 MW or More)

The Large-Scale Supply Potential Map (prepared October 30, 2026) is a document for customers planning large-scale electricity consumption. It lists substations with available capacity of 50 MW or more at a receiving voltage of 154 kV or 66 kV, and substations with available capacity of 400 MW or more at a receiving voltage of 275 kV.
Substation Surrounding area (as written in the document) Available capacity Receivable voltage
Nishi-Koshigaya Substation Around Oaza Nishiarai, Koshigaya City, Saitama Prefecture 50 MW or more 66 kV
Keihoku Substation Around Niihori (新堀), Kawaguchi City, Saitama Prefecture 50 MW or more 154 kV
Kita-Katsushika Substation Around Nakazone, Yoshikawa City, Saitama Prefecture 400 MW or more 275 kV
Shin-Sawara Substation Around Katano, Katori City, Chiba Prefecture 400 MW or more 275 kV
The approximate construction period is in 2 bands: "around 5 years" and "around 10 years." These are shown with uniform radii: for 66 kV and 154 kV, around 1.5 km from the substation is 5 years and around 6 km is 10 years; for 275 kV, around 1 km is 5 years and around 5 km is 10 years. This construction period is an indicative figure showing the construction period after the construction plan for supply has been finalized, on the premise that the application is made with the location and specifications of the receiving equipment clear. Constraints such as roads, land, and permits and approvals are not taken into account. It is stated that available capacity may have changed since the preparation date and that the specific construction period needs to be confirmed through a preliminary consultation. There is also a note that the figures may differ from the available capacity on the company's Welcome Zone Map (as of December 2025) for reasons such as the documents having been prepared at different times.

Estimating the Construction Cost Contribution

The company's page includes a simulation of the construction cost contribution for receiving power at 66 kV through a main line and a standby line. The unit construction cost is JPY 198.0 per 1 kW per 100 m for overhead lines and JPY 594.0 for underground lines. For the main line, the amount is calculated by multiplying the unit cost by the route length of the work subject to the contribution and by the newly added contracted power, and then deducting the amount borne by the company (JPY 5,500 per 1 kW). This is no more than an estimate, and the route length and the amount are decided through consultation with the company. The Large-Scale Supply Potential Map carries a note that this simulation is premised on 66 kV and that a separate preliminary consultation is required for 154 kV and 275 kV.

How to Read Kansai Transmission and Distribution's Maps

Kansai Transmission and Distribution uses the term "Welcome Zone" for areas where it can deliver electricity relatively quickly and at low cost to customers seeking high-voltage or extra-high-voltage supply for factories and the like. Its official page has a screen for viewing information on industrial sites from pins on a map, and the "Supply Availability Area Map" (PDF) for those considering large-scale supply of tens to hundreds of MW. When considering a data center, you will mainly look at the latter.

The 3 Types of Map and Their Color Coding

The Supply Availability Area Map (as of September 2026) provides information on a standard voltage of 70 kV and covers customers with contracted power of 10,000 kW or more. At the beginning there is a note that it assumes large factories, data centers, and the like seeking to receive power at 77 kV. There are the following 3 types of map.
Type of map Content
Large-Scale Supply Availability Area Map (wide-area version) Substations with available supply capacity of around 100 to 300 MW
Small-to-Medium-Scale Supply Availability Area Map (wide-area version) Substations with available supply capacity of around 10 to 50 MW
Early Supply Availability Area Map (detailed version) Shows, for each substation, areas with available capacity of 10 MW or more where supply is possible with a construction period of around 3 to 5 years
In the detailed version, available capacity of 10 MW or more and less than 30 MW is color-coded green, 30 MW or more and less than 50 MW orange, and 50 MW or more red. The same document also includes the "Contribution and Construction Period Quick-Reference Map," which shows the contribution, construction period, and suppliable capacity.

Examples of Substations Listed

In the document as of September 2026, for example, Minami-Kawachi Substation (near Betsui (別井) 2-chome, Tondabayashi City, Osaka Prefecture) is listed with available supply capacity of 389 MW, Ritto Substation (Ritto City, Shiga Prefecture) with 250 MW, Sennan Substation (near Naruai-Kita (成合北), Kumatori Town, Sennan District, Osaka Prefecture) with 193 MW, and Kita-Toyonaka Substation (near Shoji (少路) 1-chome, Toyonaka City, Osaka Prefecture) with 69 MW. Nishi-Mikuni Substation (near Nishimikuni 1-chome, Yodogawa Ward, Osaka City, Osaka Prefecture) has available supply capacity of 173 MW, but carries a note that the upper limit is less than 30 MW for both the 4-year and 5-year indicative construction periods. This means that even where the available capacity of the substation as a whole is large, the capacity usable within a few years may be small. The figures are updated, so please check the latest version of the document.

Points to Note

The points to note in the document state that supply is basically through 2 circuits, a main line and a standby line, from the same substation (this does not apply to some substations), and that the actual work may vary greatly with land conditions and road construction plans in the surrounding area. The published scope is updated from time to time, and because electricity supply may be possible even in unpublished areas, those seeking interconnection in an unpublished area are directed to apply for a preliminary study. Applicants are asked to refrain from applications that are not backed by an actual business and are aimed at securing available supply capacity. Where this is suspected, acceptance or the response may be put on hold. Submission or explanation of a business plan may also be requested before the application for a wheeling supply contract.

Steps for Moving from the Map to a Preliminary Study

Once you have narrowed down the candidates on the map, the next step is to apply to the general transmission and distribution utility for a preliminary study (a preliminary consultation at some companies) and confirm whether supply is possible at that site, the construction period, and the approximate construction cost. If you go as far as acquiring the land or signing a lease on the basis of the map alone, there is a risk of not being able to receive power at the time you assumed. The steps are as follows.

1. Decide the Power and Voltage Required

First, organize the contracted power of the data center you are planning and, if it is to be increased in stages, the power at each stage. The voltage and scale covered by the maps differ from company to company. Deciding first which class your plan falls into determines which map you should look at. Voltage classes are explained in Data Center Receiving Capacity and Extra-High-Voltage Supply (Japanese).

2. Narrow Down Candidate Areas on the Map

Look at the available capacity band, the distance from substations and transmission lines, and the indicative construction period, and identify several candidates. At the same time, check the as-of date of the map and the definition of the starting point of the construction period. Lining up several candidates rather than narrowing down to 1 site makes it easier to act if the later study result is unfavorable.

3. Apply for a Preliminary Study (Preliminary Consultation)

Apply for a preliminary study for the candidate sites. Kansai Transmission and Distribution's materials set out a flow of proceeding to the wheeling supply contract application if the site is within an area shown on the map as suppliable, and a flow from the preliminary study application through the technical study (3 months) to the response, followed by the wheeling supply contract application. TEPCO Power Grid accepts applications for the supply preliminary consultation on the web and states that the preliminary consultation may take 1 year or more. How to fill in the application form and the required documents are summarized in our article explaining the supply-side preliminary connection study.

4. Review the Response and Decide Whether to Apply or Revise

Check whether the construction period, construction cost, and receiving method shown in the response fit your business plan. If they do not, revise the capacity or carry out a fresh study at a different candidate site. In the preliminary studies we have handled, even in areas shown on the map as having available capacity, the response sometimes gives a longer construction period than assumed because of the transmission line route or the condition of the upstream grid. Through our Data Center Grid Connection Application Support, we assist with everything from checking the maps to applying for the preliminary study and interpreting the response. Fees are quoted individually according to the number of sites, the voltage class, and the scope of work.

Frequently Asked Questions About the Welcome Zone Map

Can we receive power if the area is shown on the map?

Not necessarily. The map is indicative material showing areas where supply may be possible relatively quickly. Every company notes that available supply capacity and the construction period change with grid conditions and other applications and may be changed in a detailed study. Whether power can be received at a specific site, and what the construction period and construction cost will be, is confirmed through a preliminary study (preliminary consultation) with the general transmission and distribution utility and the subsequent application. It is safer to decide on the land contract after seeing the response.

How often are the maps updated?

Within what we checked, we did not find any statement setting a uniform update frequency. The as-of date differs from company to company. As of November 17, 2026, TEPCO Power Grid's map is stated to be as of December 2025, the Large-Scale Supply Potential Map to have been prepared on October 30, 2026, Kansai Transmission and Distribution's Supply Availability Area Map to be as of September 2026, and Shikoku Electric Power Transmission and Distribution's to be as of October 15, 2026. Please check the as-of date shown each time you look.

Can the maps also be used for small high-voltage data centers?

Many of the maps cover large-scale demand receiving power at extra-high voltage. TEPCO Power Grid's covers extra-high voltage at 2,000 kW or more, and Kansai Transmission and Distribution's Supply Availability Area Map covers contracted power of 10,000 kW or more. Small projects receiving power at high voltage (6 kV) are determined largely by the condition of distribution lines and distribution substations and cannot be judged from the maps alone. For high voltage too, confirm individually through a preliminary study. For details, please see our article explaining high-voltage data centers.

How should we look into areas not shown on the map?

Not being listed does not mean that supply is not possible. Kansai Transmission and Distribution states that electricity supply may be possible even in unpublished areas and directs those seeking interconnection to apply for a preliminary study. Tohoku Electric Power Network likewise directs customers to inquire individually about points not listed. The basic way to look into it is to organize the location of the candidate site and the desired contracted power and timing, and then apply to the general transmission and distribution utility for the area for a preliminary study.

Related Articles and Services

References (Primary Sources)

* The content of this article is current as of its publication date. Later changes to rules or their operation may not be reflected, so please check the official announcements of each organization for the latest information. If you need your project checked against the latest rules, please feel free to contact us.

Reviewed by
General Manager, Energy Solutions Division, Grid Work Inc.

A licensed electrical engineer with more than ten years at a Japanese electric utility, working on substation design, construction and management. Draws on hands-on experience from the grid-operator side to support grid connection applications for power plants and grid-scale batteries, and to prepare application documents that avoid rejections.

How does this apply to your project?

Grid connection procedures differ by utility area and facility conditions. Questions at the “what would this mean for our case?” stage are welcome. Our team knows the utility-side process.